2022 development program underway for the Tiwi Green Hydrogen Project

GEV acknowledges that its proposed Tiwi Green Hydrogen Export Project is located on the traditional lands of the Munupi people. It is a privilege to have the support and such a close working relationship with the Tiwi Land Council and Munupi Landowners.
- 2022 development program underway for the Tiwi Hydrogen Project with an initial focus on environmental permitting which determines the overall timing of the project.
- Darwin based EcOz Environmental Services (EcOz) engaged to prepare the environmental Referral submission for lodgement with the NT Environment Protection Authority (NT EPA) in the first half of 2022.
- Consulting firms ILF and Jacobs have also been engaged to prepare engineering studies supporting the Referral submission, covering the key areas of solar generation, power transmission and water desalination.
- GEV continues to work with key stakeholders, including the Tiwi Land Council, the Munupi Landowners, Tiwi Plantation Corporation, NT Port and Marine and the Northern Territory Government.
- GEV’s 2022 development program is fully funded post the November 2021 capital raising.
Global Energy Ventures Ltd (ASX: GEV, the Company) is pleased to provide the following update on its 2.8 GWgreen hydrogen export project on the Tiwi Islands, Northern Territory, Australia (the Tiwi Hydrogen Project).
GEV’s Executive Director and Chief Development Officer, Garry Triglavcanin commented: “The Company is delighted with the engagement of Darwin based EcOz to prepare the environmental Referral submission on behalf of GEV. EcOz has extensive experience in Referral submissions for renewable energy projects both in the NT and the Tiwi Islands. The Referral submission is an important step forward as the environmental process is likely to drive the project schedule. There are a number of key environmental studies that can only be conducted during the current wet-season.
Further to our previously announced MOU with ILF Consulting Engineers in Germany (ILF), GEV is delighted to commence work with ILF to assist with solar generation and transmission engineering work for the Tiwi Hydrogen Project. Additional engineering will also focus on water desalination requirements to supply pure water to the electrolysis plant.”
LOW ENVIRONMENTAL FOOTPRINT
GEV continues to pursue a low environmental footprint for the Tiwi Hydrogen Project, with the proposed solar site planned to be constructed on existing plantation land, and the hydrogen production, compression and loading facilities proposed to be built on existing industrial precinct / existing port area. For the Referral submission to reflect this view, consultants have now been engaged to undertake engineering studies for the key components, being the transmission line route and water desalination.
The purpose of the Referral submission is to provide sufficient information to the NT Environment Protection Authority (NT EPA) so that a decision can be made on the level of assessment required for the Tiwi Hydrogen Project. GEV expects to lodge its Referral submission in the first half of 2022.
ENGINEERING STUDIES SUPPORTING THE REFERRAL SUBMISSION
The engagements by GEV of Jacobs Group (Australia) Pty Ltd (water desalination) and ILF (transmission line) are especially important at this time, as they address two key environmental impact areas of the Tiwi Hydrogen Project, being the brine discharge from the proposed desalination plant; and the environmental impact of clearing the ~30 kilometre transmission line corridor. The engineering study to be undertaken by Jacobs will include both near and far field modelling of the brine discharge.
These studies will assist GEV in demonstrating to both the NT EPA and the Tiwi people that the brine discharge and transmission line corridor maintains a low environmental impact, being a material advantage of the Project. GEV will continue to provide updates as further engagements are made.
NEXT STEPS
The Company continues to work closely with the Tiwi Land Council, Munupi Landowners and the Tiwi Plantation Corporation for land access requirements to support the project, including the solar site and transmission corridor. The Northern Territory Government has also appointed a Case Manager to the Tiwi Hydrogen Project to support GEV’s interface and requirements with relevant government agencies.
GEV will advance discussions with suitable groups to support the detailed engineering of the solar generation and electrolysis for the production of green hydrogen. Appointments will be made during the March and June quarters to commence detailed engineering, including experienced renewable project resources, to support the target of financial close (of the initial phase) by mid-2023.
The Company will also get underway with preliminary marketing activities of green hydrogen from the Tiwi Hydrogen Project in the March quarter, with a number of strategies to identify relevant parties for potential offtake in the markets of Singapore, Japan, Korea and Indonesia.
Figure 1: Tiwi Hydrogen Project Overview
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved