Crete-Peloponnese Interconnection: The largest subsea AC cable in the world has been electrified

IPTO successfully electrified the first subsea cable linking Crete to the mainland power grid, which is also the largest subsea AC interconnection in the world.
The completion of the 24-hour test electrification signifies a historical success for the Operator and the contractors, as they faced up to the significant technological challenges with effectiveness and technical efficiency, transcending -to a considerable extent- what has been achieved so far in similar international projects.
It is noted that the eastern circuit of the interconnection, that was electrified, consists of the following subprojects:
1. Submarine cable with a length of 132 km between Chania, Crete and Neapoli, Lakonia (Contractor: PRYSMIAN),
2. Underground cables with a length of 42 km in Crete and Peloponnese (Contractors: HELLENIC CABLES S.A. and FULGOR S.A.),
3. New substation in eastern Peloponnese and upgrading of the existing substation in Chania (TERNA S.A.).
The power link of Crete and Peloponnese is called the “interconnection of the records” as it is:
– The longest AC cable interconnection in the world (174 km).
– The longest submarine high voltage interconnection in the world with a triplex cable of XLPE isolation (132 km).
– The deepest submarine high voltage interconnection in the world with a triplex cable of XLPE isolation (at a depth of 1,000 m.).
The project also entails important management difficulties, as the new interconnection extends from Megalopolis all the way to Chania and Heraklion, Crete, including a total of eight towns in its design. In this respect, IPTO consulted with local bodies and authorities aiming to mitigate potential nuisances and search for optimal solutions, such as undergrounding of transmission lines, where possible.
The project has a total budget of 356 million euros and is being implemented with the co-financing of Greece and the European Union as well as a loan from the European Investment Bank (EIB).
Mr. Kostis Hatzidakis, Minister for Environment and Energy stated:
“The test electrification of Crete-Peloponnese interconnection means that crucial infrastructure, not only for Crete but for the country in general, is just one step away from its completion. It is a milestone for the planning of island interconnections, as they are truly “green” projects with an exceptionally positive environmental and socio-economic footprint. That is why the Ministry of Environment and Energy supports the acceleration of these projects, which will also be financed by the Recovery Fund.”
Mr. Manos Manousakis, President and CEO of IPTO, commented in this regard:
”The first interconnection of Crete with the mainland system is a reality. After the completion of the trial electrification we can definitely say that the “energy exclusion” of Crete is now lifted. We are very satisfied about the fact that we managed to electrify the “interconnection of the records”, precisely two years after the signing of the relevant contracts. We accomplished it thanks to the devotion of our employees, despite the adversities and the technical challenges. With the timely implementation of emblematic projects, IPTO meets the challenge of electric interconnections in defiance of the pandemic crisis.”
Related News.
September 24, 2026
Cyprus Marine Club Welcomes a Full House for Aphentrica’s War Risks Presentation
The Cyprus Marine Club marked its return after the summer break with a full house at Gazebo Mare on Tuesday, 22 September, bringing together members,…
September 24, 2026
IMO seeks feedback on Maritime Single Window implementation
The International Maritime Organization (IMO) has launched a global survey to assess the implementation and use of Maritime Single Windows (MSWs),…
September 24, 2026
World Maritime Day industry panel to examine the gap between maritime policy and the reality of life at sea
OneCare Group will bring together crewing, safety, insurance and wellbeing specialists for a World Maritime Day webinar examining how shipping can…
September 24, 2026
IUMI President – Marine insurers are war insurers
Marine insurers are at the heart of managing war risks to global shipping and must continue to develop the tools needed to support and facilitate…
September 24, 2026
Seafarer welfare is improving amongst leading companies, but five years of evidence shows this progress is far from the norm
Five years on, the Seafarers’ Rights Code of Conduct is driving more than 1,000 companies to participate in RightShip’s Crew Welfare…
September 24, 2026
The UK ETS arrives for shipping what it means for charterers
Introduction The UK Emissions Trading Scheme (UK ETS) was extended to domestic maritime activity on 1 July 2026, following the EU ETS, FuelEU…
September 24, 2026
ABP Southampton invests locally with Marine Cranes to boost capability
Associated British Ports , the UK’s largest port operator, has invested a new marine deck crane aboard Spartina, one of the Port of Southampton’s…
September 24, 2026
BIMCO Shipping Number of the Week
Caribbean Basin crude oil and heavy product exports jump 45% “Seaborne exports of crude oil and heavy products from the Caribbean Basin have…
September 24, 2026
xclusiv S&P Report 21th September 2026
Pls find below the [xclusiv] S&P Report 21th September 2026 [xclusiv] 2026_09_21
September 24, 2026
Marine insurance supply remains stable as geopolitical and technical changes reshape the market, says IUMI President
The global marine insurance market remains in a stable position, with premium growth strongly supported by a weak USD in hull and cargo. Meanwhile…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved