Reliability, flexibility and sustainability of Wärtsilä technology lands repeat order from Nigerian cement producer

The technology group Wärtsilä will supply a 70 MW captive power plant for the BUA’s new Sokoto cement production plant in Nigeria. The new plant is required to supply the energy for an off grid additional cement production line. This follows an order for a 50 MW power plant from the same customer just two years earlier. This latest extended engineering and equipment order was booked in Wärtsilä’s order intake in October 2021.
Both the current and 2019 orders feature Wärtsilä 34DF dual-fuel engines operating primarily with liquefied natural gas (LNG), but with the flexibility to switch to an alternative fuel oil should there be interruptions to the gas supply, quality or pressure. Operation of the Wärtsilä engines is not affected by these interruptions.
“To maintain our cement production requirements in line with our schedules and economic forecasts, we need reliable, fuel-efficient power generation. We also need capable and reliable after-market support, and in all these areas Wärtsilä is a strong partner with their local presence to provide excellent service. The decision to issue a repeat order for the new power plant from Wärtsilä was not, therefore, difficult to make,” commented Abdul Samad Rabiu, CON, Chairman, BUA Cement and BUA Group.
“Wärtsilä’s dual-fuel engine technology is particularly valuable where the primary fuel supply cannot be totally trusted. The flexibility and reliability of our solution were major considerations in the award of this contract, added to which the ability to operate on LNG considerably lessens the facility’s carbon footprint,” said Marc Thiriet, Energy Business Director, Africa West, Wärtsilä.
BUA Group, through its cement subsidiary, BUA Cement Plc, is one of Nigeria’s largest cement producers with operations spread across Nigeria. In addition to the environmental sustainability benefit, it is estimated that the Wärtsilä solution will result in fuel cost savings of approximately 30 percent compared to the existing power plants operating on heavy fuel oil (HFO). Furthermore, the operational flexibility of the Wärtsilä engines provides future-proofing advantages enabling the potential use of energy from renewable sources, such as solar and wind.
The plant will operate on seven Wärtsilä 34DF engines scheduled for delivery mid-2022. The plant is expected to be fully operational in 2023.
Wärtsilä holds a strong position in Nigeria’s power generation market. Together with its installed base, this and other orders will bring the company’s share to more than 800 MW. On the African continent as a whole, Wärtsilä has an installed base of more than 7000 MW.
Related News.
November 24, 2026
Greece has the most to lose from delays in shipping’s green transition, new analysis finds
UCL and WWF Greece report finds the IMO Net-Zero Framework offers Greek ship owners the clarity they need, and the best protection against a…
November 24, 2026
Snow Land joins Cool Carriers as the world’s first reefer with a gate rudder, a new chapter for sustainable and efficient reefer shipping
Cool Carriers, the world’s largest operator of specialised reefer vessels, took delivery of Snow Land from Kitanihon Shipbuilding in Japan on 12…
November 24, 2026
IBIA launches Marine Energy Outlook Survey as Annual Convention in New York
IBIA - The International Bunker Industry Association officially launched its Marine Energy Outlook Survey during the IBIA Annual Convention in New…
November 24, 2026
Why did ITF staff vote to strike again?
Staff at the International Transport Workers’ Federation (ITF) headquarters in London have voted to give their union a strike mandate. According to…
November 24, 2026
Nearly half of maritime crew tickets booked a week ahead are cancelled
Two new C Teleport reports show when maritime and aircrew teams book crew flights, how often they cancel, and what late booking costs, with a…
November 24, 2026
Kpler completes $1.5bn+ Sixth Street investment and continues accelerating growth
Investment backs Kpler's bold ambition to shape the future of global trade intelligence. Kpler, a leading provider of global physical trade…
November 24, 2026
How SAL and DNV are strengthening heavy-lift shipping
From classification and newbuilding support to operational tools and advisory expertise, SAL and DNV have been collaborating for decades. The…
November 24, 2026
PSA Singapore breaks ground on Tuas Port Phase Two to strengthen Global Trade Connectivity
PSA Singapore marked the groundbreaking of Tuas Port Phase Two, a significant step in the development of the world’s largest fully automated…
November 24, 2026
BIFA welcomes UK–EU trade progress and calls for clarity on implementation
The British International Freight Association (BIFA) has welcomed progress made at today's UK–EU Summit in Brussels, highlighting the potential…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved























…