Var Energi provides a schedule update for the Balder X development project

The target production start has been moved to the second quarter 2025.
As previously communicated, the revised plan has limited impact on the Company’s 2024 production and no material impact on guided capital costs. The Company’s end-2025 production target of around 400 thousand barrels of oil equivalent per day (kboepd) is not affected by the updated project start-up.
A key consideration has been to limit the carryover work into the offshore installation and start-up phase as much as possible. Together with our suppliers we have made every effort to complete the final work on the Jotun FPSO at the Rosenberg yard to enable field installation before the winter weather period. However, despite recent good progress, some onshore completion and commissioning work required prior to sail-away remains. Although achieving first oil by end of the fourth quarter 2024 is no longer possible this has limited impact on 2024 production and our guidance of 280-300 kboepd for the year is maintained, says CEO of Vår Energi, Nick Walker.
With all development wells completed and all subsea production systems installed, the plan is now to complete the FPSO vessel fully onshore, enabling first oil within the second quarter next year. As part of the decision not to sail, the cost basis for the project has been updated reflecting a sail-away in the spring of 2025, this represents an additional project cost of around USD 400 million gross pre-tax (NOK ~4.27 billion¹) of which approximately 75% will be incurred in 2025.
The Company’s capital spend guidance for 2024 is revised down from USD 2.7-2.9 billion to around USD 2.6 billion, reflecting other cost reductions and a favourable NOK exchange rate. Vår Energi’s production target for 2025 remains unchanged and the Company is on track to reach around 400 kboepd by end of next year.
Balder X, will secure production from the Balder Area beyond 2045, unlocking gross proved plus probable (2P) reserves of around 150 million barrels of oil equivalent (mmboe) and with a gross peak production of 80 kboepd².
The Jotun FPSO will be an area host, enabling future growth opportunities. Balder Phase V is being progressed, including the drilling of six production wells to utilise the remaining subsea template well slots to capture gross 2P reserves of more than 30 mmboe. Drilling of these wells will commence in the first half of 2025 and be completed in 2026. In addition, the Balder Phase VI project is being matured, to add new subsea facilities and wells, with expected investment decision planned first half of 2025. There remains significant additional resource upside in the area and further exploration drilling and tie-back development phases are being planned.
Vår Energi is operator (90%) of the Balder Area with Kistos Energy (Norway) AS as partner (10%).
Related News.
October 27, 2026
Beyond Compliance to Uninterrupted Operations: Delia Shipping’s Konstantinos Stais on Maritime Cyber Resilience, LEO Expansion, and AI Governance
As the global maritime industry navigates an era of intense digital acceleration, the traditional boundaries separating shipboard operational…
October 27, 2026
Chinese AI quietly writes hackable code for Beijing’s Adversaries, even when run locally, study finds
Qwen3-Coder wrote hackable apps 19% more often for US defense contractors and leaked data 28% more often for Hong Kong activists, AI security firm…
October 27, 2026
Industry leaders launch world’s first maritime-specific cyber vulnerabilities database
Cydome, ClassNK, Bureau Veritas, MTS-ISAC and Rakuten Maritime announce the “Blue Initiative”, an open collaboration to improve maritime cyber…
October 27, 2026
Businesses increasingly adopt AI for cybersecurity while individuals expand privacy protections
As cyber threats grow and digital technologies become more pervasive, businesses are increasingly using AI to strengthen…
October 27, 2026
EmissionLink calls for EU ETS revenues to fund maritime carbon capture trials and port infrastructure
Maritime emissions specialist, EmissionLink, has called for a dedicated proportion of EU Emissions Trading System (EU ETS) revenues to be invested…
October 27, 2026
Port of Antwerp-Bruges sees strong recovery in container throughput in volatile trading environment
In the first nine months of 2026, Port of Antwerp-Bruges handled 200.9 million tonnes of goods, 0.8% less than in the same period last year.…
October 27, 2026
Sanctions risks reshape commodity trading
Traders face sanctions challenge “odyssey” as geopolitical risks reformat global markets Commodity traders are operating in an increasingly…
October 27, 2026
Titan analysis shows FuelEU pooling propelled liquefied biomethane demand
- Clean fuel supplier evaluates compliance for 8,000 TEU containership operating in Northern Europe - FuelEU Maritime balances competitiveness…
October 27, 2026
Russian diesel tanker heads to New York as Kremlin claims regular shipments
Malta-flagged tanker should carry 40,000 mt fuel Agioi Fanendes left Primorsk Oct. 22: CAS US lifts sanctions, enables Russian imports……
October 27, 2026
Pilot transfer operation: A safer step aboard
Safe pilot transfer operations depend on both correct procedures and fit-for-purpose equipment. New SOLAS requirements entering into force in…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved