Allseas awarded Troll extension pipeline

June 17, 2024

Allseas will install the pipeline and integrated structures for the second development stage of Equinor’s Troll Phase 3 project that will accelerate the production and contribute to maintain the high production capacity utilisation of Troll A Platform and Kollsnes onshore plant towards 2030.

Phase 3 development will enable gas production from the Troll West field via subsea tiebacks to the original Troll A platform, approximately 80 kilometres northwest of Bergen, Norway.

For Stage 2, Allseas will install a 28-kilometre, 36-inch concrete-weight-coated gas line parallel to the Stage 1 pipeline, installed by our pipelay vessel Solitaire  in 2020. The new pipeline will contain three inline tees, one for future tie-in flexibility.

The latest Troll award includes fabrication and assembly of multiple pipeline heads and the inline tees, installation and retrieval of counteracts, and flooding, cleaning and gauging of the pipeline system. Execution is planned with Pioneering Spirit in 2026.

Related News.

Subscribe to our newsletter!

if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!

* indicates required
Consent *
By submitting this form you agree to receive Email Marketing

Design & Development by P.KAN.DESIGNER

Design & Development by P.KAN.DESIGNER

Privacy Preference Center