Equinor updated cost estimate for the Snøhvit Future project

On behalf of the partnership, Equinor has updated the cost estimate for Snøhvit Future to NOK 26.5 billion in 2026 value. The timetable for the project remains unchanged, with onshore compression planned to start in 2029 and electrification in 2030.
The updated figures for Snøhvit Future have been reported to the Ministry of Energy in connection with the government’s proposed national budget for 2027.
In December 2025, Equinor announced an updated cost estimate for the project of just over NOK 20 billion in 2025 value. When the plan for development and operation (PDO) was submitted in 2022, the investment estimate was NOK 13.2 billion. Adjusted to today’s NOK value, this corresponds to NOK 15.2 billion.
“We take the cost development of Snøhvit Future seriously. The project is being carried out at an operating facility and is more complex than anticipated. It has also been affected by unforeseen issues and challenges,” says Trond Bokn, Equinor’s senior vice president for project development.

He points out that operational challenges at the Hammerfest LNG plant, weather conditions and difficult rock conditions in the power cable tunnel have affected progress and costs.
“We have worked closely with the suppliers to manage the complexity of the project and work together every day to deliver the project safely and efficiently. Snøhvit Future is still a profitable project that supports jobs in Hammerfest, Norwegian value creation and energy supply to Europe towards 2050,” says Bokn.
Equinor expects the work on Snøhvit Future to continue to be demanding. The project and the suppliers are implementing targeted measures, systematic risk management and close integration with the operating plant.
The project serves two purposes. Onshore compression will help maintain plateau production at Hammerfest LNG when reservoir pressure declines. Electrification of Hammerfest LNG will cut annual CO₂ emissions by 850,000 tonnes, equivalent to two per cent of Norway’s annual emissions.
Snøhvit Future is about 60 per cent complete. The compressor module was installed in August, and there is a high level of activity at Melkøya, in the tunnel project and among suppliers. In the development phase, it is expected that more than 70 per cent of value creation will go to Norwegian companies. More than a third of this will go to Northern Norway.
Snøhvit partnership: Equinor Energy AS 36.79%, Petoro AS 30%, TotalEnergies EP Norge AS 18.4%, Vår Energi ASA 12%, Harbour Energy Norge AS 2.81%
Related News.
October 12, 2026
ONE DAY LEFT until the CSN London Maritime Forum “Shipping: Predicting an Unpredictable Future” – REGISTER NOW
“Shipping: Predicting an Unpredictable Future” REGISTER HERE Date: 13 October 2026 Time: 09:00-15:00 Venue: Marriott Hotel Regent's Park Following…
October 12, 2026
Eliana Savvidi, General Counsel at InterMaritime Shipmanagement recognised in the Legal 500 GC Powerlist: Greece & Cyprus 2026 for the 6th Consecutive Year
Eliana Savvidi, General Counsel at InterMaritime Shipmanagement Ltd., has been recognised in the Legal 500 GC Powerlist: Greece & Cyprus 2026 –…
October 12, 2026
Singapore strengthens ship registry capabilities as Registry marks 60 Years
The Singapore Registry of Ships (SRS) is strengthening its capabilities to support a more digital and increasingly multi-fuel shipping sector, as it…
October 12, 2026
Wallenius Marine takes the next step for wind-powered shipping in new research project
Wind is once again set to become one of shipping’s most important sources of energy. To accelerate this development, Wallenius Marine, together with…
October 12, 2026
Developing autonomous systems to secure Norwegian ports
As the Norwegian Police Security Service (PST) urges coastal communities to remain vigilant for suspicious activity and raises concerns about…
October 12, 2026
Hormuz: Normalisation no longer needs to wait for a deal
Kpler is moving away from the assumption that reopening the Strait of Hormuz requires a comprehensive political agreement. Our base case will…
October 12, 2026
MarinePALS and SEAker to link cadet training records with verified sea service
MarinePALS and SEAker have signed a Philippine distribution agreement to connect digital cadet training records with verified sea service. The…
October 12, 2026
DP World reaffirms long term partnership with India as executive chairman H.E. Essa Kazim makes first visit
Executive Chairman H.E. Essa Kazim, Group CEO Mr. Yuvraj Narayan and members of the board engage with JNPA leadership to explore opportunities for…
October 12, 2026
Sarjak Container Lines opens Ahmedabad Office to strengthen its Western India operations
Sarjak Container Lines , part of the Saksham Group of Companies, has expanded its presence in Gujarat with the opening of a new office in Ahmedabad,…
October 12, 2026
SFL announces sale of four LR2 and three Suezmax tankers, and termination of charters
SFL Corporation announced that it has agreed to sell four 2014- and 2015-built LR2 product tankers and three 2019-built Suezmax tankers, currently on…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved