Mammoet Offshore jack-up rig leg extension works completed ahead of schedule

First deployment of a CC8800-1 Boom Booster configuration in the UAE helps to extend working life of an offshore asset, maximizing its value.
Mammoet has successfully completed a series of heavy lifting operations as part of the Rig BW Maromba B WHP conversion project at Drydocks World Dubai.
The project involves the conversion of the former VALARIS 247, a heavy-duty jack-up drilling rig being repurposed into a wellhead platform for deployment at the Maromba field offshore Brazil.

Commissioned by Drydocks World, Mammoet provided engineering, equipment and specialist personnel to lift and install nine rig leg extension sections. The scope involved three legs, each consisting of three triangular sections weighing approximately 105t and measuring 10.2m in height and 16.2m in width.
A key milestone for the project was the first deployment of this CC 8800-1 Boom booster crane configuration in the United Arab Emirates. Configured with a 120-metre main boom and a 96-metre luffing jib, the crane delivered the hook height and lifting performance required to safely install the leg extension sections.
The Boom Booster, fitted to the crane’s main boom, extended its lifting capability, allowing heavy components to be lifted to greater heights and at longer working radii without the need for a larger crane.
A comprehensive engineering package, including lifting studies, ground bearing pressure calculations and detailed execution procedures, ensured every lift could be planned and executed safely within the operational constraints of the shipyard environment.
The project increased the height of all three rig legs from 175m to 205m, enabling the converted platform to operate at its future offshore location. The lifting works were completed ahead of schedule.
“The BW Maromba B WHP conversion project is an important project for Drydocks World, bringing together our engineering, fabrication and project delivery teams to prepare the platform for its next operational life,” said Ajith Puthenveettil Ramachandrakurup, Senior Project Manager at Drydocks World. “The successful completion of the rig leg extension works is a significant milestone in that journey. We appreciate Mammoet’s contribution in providing the specialist heavy lifting expertise required to safely execute this phase of the project.”

“Repurposing offshore assets is becoming an increasingly important way for operators to extend the life of existing infrastructure, maximize the value of previous investments and reduce the need for new construction,” said Samar Iqbal, Project Manager at Mammoet.
“We’re proud to support Drydocks World on the Rig BW Maromba B WHP conversion project, applying our engineering expertise and heavy lifting capabilities to help prepare the platform for its next phase of operation”.
Once the conversion program is complete, the BW Maromba B wellhead platform is expected to be deployed at the Maromba field offshore Brazil, supporting the next phase of the development.
Related News.
October 16, 2026
Navigating the Multi-Orbit Era: In Conversation with Intellian’s Jon Harrison at SMM 2026
At SMM 2026 in Hamburg, the rapid evolution of maritime satellite communications took centre stage. Across the exhibition halls, discussions among…
October 16, 2026
Cyprus ports need joint energy and investment strategy, shipping agents chief says
Cyprus needs a coordinated strategy for shipping, energy and environmental protection to support port investment and modernisation, Cyprus shipping…
October 16, 2026
MASO Public Affairs introduces MASO Regulatory Intelligence
A new subscription service helping businesses understand what is changing and what it means for them MASO Public Affairs introduces MASO Regulatory…
October 16, 2026
Anglo-Eastern helps turn CMBTECH’s ammonia ambition into an operational reality
From early feasibility study and risk-based design to newbuilding supervision, crew readiness and technical management, Anglo-Eastern drew on its…
October 16, 2026
Escalation of attacks threatens to derail recovery in Middle East oil exports
World oil demand is forecast to fall by 2.5 mb/d y-o-y in 4Q26 and 2.6 mb/d on average in 2026. As the Iran war manifests itself through restricted…
October 16, 2026
New study finds shipping pays twice its share to EU ETS earmarked revenues should triple to help build market for sustainable fuels and technologies
Shipping is responsible for around 10% of EU ETS emissions but pays almost 20% of the ETS bill. Unlike other sectors, it has never received free…
October 16, 2026
MSARC strengthens maritime mass rescue readiness through training and national live exercise off Dakar, Senegal
Joint MSARC–FHAS programme combines three days of SAR training with a national multi-agency live exercise The Maritime Search and Rescue Council ,…
October 16, 2026
Sogese report deliveries are still being delayed as container freight rates fluctuate
FOR IMPORTERS Spot rates into the Mediterranean are back at January levels, Far East to Europe reliability sits at pandemic lows, and nearly…
October 16, 2026
Glencore begins trading on Australian Securities Exchange
Glencore has begun trading on the Australian Securities Exchange under the ASX code GLC. Gary Nagle, Glencore’s CEO, said it was an exciting day for…
October 16, 2026
BIMCO Shipping Number of the Week
Suez Canal container ship transits exceed 50% of pre-disruption levels "During the first two weeks of October, weekly container ship capacity…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved