Equinor supply more gas for 30-year-old Troll A

The Troll A platform in the North Sea is being supplied with additional gas. On 22 August production started from the Troll Phase 3 stage 2 subsea project.
This helps maintain jobs, value creation and high gas deliveries to Europe from Troll A and the Kollsnes processing plant, which marks its 30th anniversary this year.
The project accelerates production of 55 billion standard cubic metres of gas from the Troll West reservoir. This corresponds to nearly two years of France’s gas demand.

“Troll is the backbone of Norwegian gas exports to Europe. This project accelerates production from the reservoir, helping maintain today’s high level of gas exports from Troll and Kollsnes for as long as possible. With both Troll A and the Kollsnes gas plant powered by electricity from shore, the gas is produced with very low emissions,” says Lill Harriet Brusdal, vice president for Troll and Kvitebjørn.
The Trollpartnership consists of Petoro, Equinor, Shell, TotalEnergies and ConocoPhillips.
Troll Phase 3 stage 2 builds on the subsea facilities from the Troll Phase 3 project, which came on stream in 2021, reusing design and standardised solutions. This reduces execution time and costs and points the way for future subsea developments. Troll Phase 3 stage 2 comes on stream just over two years after the partnership’s investment decision.
“We start production with excellent HSE results, ahead of schedule and several hundred million Norwegian kroner below the cost estimate. The main reasons are efficient marine operations and a highly efficient drilling campaign, which was completed 25 per cent faster than planned,” says Trond Bokn, senior vice president for project development in Equinor.

The Troll phase 3 step 2-project was originally scheduled to start up towards the end of the year, and the cost estimate was NOK 12.3 billion.
The eight-well drilling campaign was completed in five and a half months by the Deepsea Aberdeen rig from Odfjell, with services from SLB and Baker Hughes. Templates and manifolds were built by Aker Solutions in Egersund for main supplier OneSubsea and installed on the field by Ocean Installer.
The umbilical, supplied by OneSubsea in Moss, and the MEG line have been extended from the existing facilities. A 28-kilometre, 36-inch pipeline was installed by the world’s largest pipelay vessel, Pioneering Spirit, and the line pipe was stored on Stord. Randaberg Industries delivered spools and pipeline end terminations, and Aker Solutions has carried out modifications on Troll A.
In this way, the project has generated significant ripple effects in Norway. In operations it helps maintain secure gas deliveries to Europe, jobs and revenues for society. More than 90 per cent of the profits from the Troll field go to the state through taxes and direct ownership in the field via Petoro.
Related News.
October 16, 2026
Navigating the Multi-Orbit Era: In Conversation with Intellian’s Jon Harrison at SMM 2026
At SMM 2026 in Hamburg, the rapid evolution of maritime satellite communications took centre stage. Across the exhibition halls, discussions among…
October 16, 2026
Cyprus ports need joint energy and investment strategy, shipping agents chief says
Cyprus needs a coordinated strategy for shipping, energy and environmental protection to support port investment and modernisation, Cyprus shipping…
October 16, 2026
MASO Public Affairs introduces MASO Regulatory Intelligence
A new subscription service helping businesses understand what is changing and what it means for them MASO Public Affairs introduces MASO Regulatory…
October 16, 2026
Anglo-Eastern helps turn CMBTECH’s ammonia ambition into an operational reality
From early feasibility study and risk-based design to newbuilding supervision, crew readiness and technical management, Anglo-Eastern drew on its…
October 16, 2026
Escalation of attacks threatens to derail recovery in Middle East oil exports
World oil demand is forecast to fall by 2.5 mb/d y-o-y in 4Q26 and 2.6 mb/d on average in 2026. As the Iran war manifests itself through restricted…
October 16, 2026
New study finds shipping pays twice its share to EU ETS earmarked revenues should triple to help build market for sustainable fuels and technologies
Shipping is responsible for around 10% of EU ETS emissions but pays almost 20% of the ETS bill. Unlike other sectors, it has never received free…
October 16, 2026
MSARC strengthens maritime mass rescue readiness through training and national live exercise off Dakar, Senegal
Joint MSARC–FHAS programme combines three days of SAR training with a national multi-agency live exercise The Maritime Search and Rescue Council ,…
October 16, 2026
Sogese report deliveries are still being delayed as container freight rates fluctuate
FOR IMPORTERS Spot rates into the Mediterranean are back at January levels, Far East to Europe reliability sits at pandemic lows, and nearly…
October 16, 2026
Glencore begins trading on Australian Securities Exchange
Glencore has begun trading on the Australian Securities Exchange under the ASX code GLC. Gary Nagle, Glencore’s CEO, said it was an exciting day for…
October 16, 2026
BIMCO Shipping Number of the Week
Suez Canal container ship transits exceed 50% of pre-disruption levels "During the first two weeks of October, weekly container ship capacity…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved