First phase of Yangtze Canal widening completed, next phase underway

The first phase of the Yangtze Canal widening project in the Netherlands has been completed. The contractor consortium comprising Hakkers, De Klerk and Van Oord has delivered a new tugboat quay with twelve berths and shore power facilities. To facilitate this, the Yangtze Canal was widened by 500 metres along its southern side. The contractor consortium has now commenced work on the second phase of the project: the construction of 1,450 metres of quay wall with twenty new inland shipping berths, including shore power facilities. The successful completion of the first phase and the swift start of the second phase highlight the strong collaboration within the contractor consortium and with the Port of Rotterdam Authority.
The largest container vessels sail through the Yangtze Canal to and from the APMT 2 and RWG terminals in the Prinses Amaliahaven. Both terminals are currently expanding their capacity. As a result, traffic in the Yangtze Canal is expected to increase significantly in the near future, making it necessary to create additional space for the safe passage of increasingly larger vessels. To achieve this, the navigational channel (at seabed level) of the Yangtze Canal will be widened along its entire length over the coming years. Once the project has been completed, the Yangtze Canal – and therefore access to the Maasvlakte – will be ready to safely and efficiently accommodate the next generation of container vessels currently under development.
Second phase underway
Following the completion of the first phase, work on the second phase began immediately. This phase involves the construction of 1,450 metres of quay wall west of the existing Antarctica Quay, creating 20 additional inland shipping berths alongside the 10 existing berths. A heavy load zone will also be constructed to facilitate the one-off transhipment of goods or specific materials.
The inland shipping berths along the quay wall will have a Nautically Guaranteed Depth (NGD) of NAP -6.80 metres. To widen the navigational channel and create the new inland shipping berths, 1.4 million cubic metres of sand will be dredged and reused for land reclamation on Maasvlakte 2. These works will enable two-way traffic for container vessels of up to 24,000 TEU.
Sustainable quay wall
The upper section of the new quay wall will be constructed using approximately 10,000 m³ of geopolymer concrete. This material contains no cement and reduces CO₂ emissions by around 50 per cent compared with conventional concrete. In this way, the project supports the Port of Rotterdam Authority’s ambition to further enhance the sustainability of port infrastructure construction and maintenance.
The Port of Rotterdam Authority manages approximately 80 kilometres of quay walls and 200 kilometres of embankments. In the coming years, further investments will be made in new and replacement quay walls, with geopolymer concrete expected to be used increasingly often
Related News.
November 26, 2026
Poland’s additional national requirements distort competition says Danish Shipping
Poland has introduced a national survey requirement for smaller foreign-flagged vessels operating in Polish waters. This creates significant…
November 26, 2026
Battery Vessels could help electrify most of Global Shipping Emissions
Battery-electric ships are economical only if the pack is cycled frequently, so they have been confined to short-sea, ferry and harbour vessels…
November 26, 2026
Mintra and Ledgid explore collaboration to connect Maritime digital identity, learning and workforce development
Mintra® and LEDGID are exploring opportunities to bring together complementary capabilities in digital learning, maritime training, professional…
November 26, 2026
World Shipping Council calls for global agreement on shipping emissions as industry investment surpasses $200 billion USD
The World Shipping Council (WSC) is calling on governments to agree on binding global greenhouse gas regulations for international shipping without…
November 26, 2026
What happened to the ITF whistleblower’s complaint?
In January 2026, a whistleblower complained that International Transport Workers’ Federation (ITF) General Secretary Stephen Cotton had manipulated…
November 26, 2026
Growing regulatory scrutiny puts seafarer wellbeing firmly on maritime safety agenda, VIKAND warns
Seafarer wellbeing is coming under greater regulatory scrutiny as international rules and guidance increasingly recognise crew health and welfare as…
November 26, 2026
Good Times Bad Times the Premium Stays with the Strait
In October, we wrote that if the transfer network off Oman kept pace, Gulf crude would carry China's refill and keep drawing tonnage east,…
November 26, 2026
Allied Weekly Market Review Week 47
Pls find below the Allied - Weekly Market Review - Week 47 ALLIED - Weekly Market Report- Week 47
November 26, 2026
Intermodal Report Week 47 2026
Intermodal Report - Week 47 2026 Intermodal Report Week 47 2026
November 26, 2026
Climate TRACE releases September 2026 Emissions Data
Climate TRACE reported that global greenhouse gas (GHG) emissions for the month of September 2026 totaled 4.7 billion tonnes CO₂e. This remains…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved