Emergency power system: Will it work in a blackout?

Findings from the Tokyo MoU and IACS indicate that routine testing may not reflect how emergency power systems perform during a real loss of main power. Inadequate testing can leave critical systems unproven and create a false sense of readiness among crew when it matters most.
What the rule says
All SOLAS ships must have a self-contained emergency source of electrical power that connects automatically to the emergency switchboard if the main power supply fails. Where this source is an emergency diesel generator (EDG), it must start automatically so that essential safety systems continue to operate without delay. SOLAS further requires arrangements to be in place for periodic testing of the complete emergency power system. These requirements are set out in SOLAS Chapter II-1 Regulations 42 and 43 for passenger and cargo ships, respectively.
Where testing falls short
The Tokyo MoU first raised the issue after Port State Control (PSC) inspections, which found several EDGs performing as expected during routine tests but failing to respond correctly when tested under more realistic conditions. When a controlled blackout was initiated by opening the main switchboard bus tie, some emergency generators did not start automatically, supply transitional power, or connect to the emergency switchboard. This indicates that simulated blackout testing using devices such as “sequential test” selectors or “routine test switches” may not reflect how the emergency power system will respond during an actual loss of main power.
IACS subsequently carried out a Concentrated Inspection Campaign (CIC) on emergency power supply in 2025, covering more than 36,000 ships. While deficiencies were identified on a relatively small proportion of ships, the campaign highlighted three areas of concern:
-
Equipment failures: Recurring and critical failures were identified in components such as quick-closing valves, control units and circuits, and EDG starting arrangements. These point to potential weaknesses in equipment maintenance, installation quality, or component reliability, and may compromise the automatic activation of the emergency power supply required under SOLAS.
-
SMS and test procedures: Non-equipment deficiencies included the absence of controlled blackout test procedures in company and shipboard Safety Management Systems (SMS). This is significant, as SOLAS requires periodic testing of the complete emergency power system. As highlighted by the Tokyo MoU, commonly used simulated blackout tests may not verify the actual circuit paths and automatic functions required during a real loss of main power. In IACS’ words, this “gives ship’s engineers a false sense of readiness of the ship’s emergency systems.”
-
Crew familiarity: The findings also point to gaps in crew familiarity with EDG operation, including incorrect selection of starting switch modes. This underlines that emergency power readiness depends not only on equipment condition and test design, but also on crew competence and safety culture.
Recommendations
Ship operators should use the campaign findings to critically review whether emergency power testing, maintenance and inspection, and crew training are sufficient to demonstrate that the complete system will work during a real blackout. Testing must verify system-level functionality in line with SOLAS requirements. In particular, operators should liaise with their classification societies and ensure that:
-
controlled blackout test procedures are sufficiently detailed in company and shipboard SMS,
-
critical components such as valves, control systems and generator starting arrangements are maintained and tested at appropriate intervals, and
-
crew are familiar with emergency generator operation in practice, including correct configuration and response during a blackout scenario.
In Gard’s experience, realistic blackout testing should not stop at confirming that the emergency diesel generator starts and connects to the emergency switchboard. Tests should also demonstrate that the generator can run reliably and carry the required load for a sufficient period. Particular attention should be paid to the type and condition of fuel in the EDG service tank, ensuring that it remains suitable for use under expected operating conditions. Experience shows that an EDG may start as intended but fail or stop after a short period, or be unable to run at rated load, due to clogged fuel oil filters.
We also recommend that operators review uninterruptible power supply (UPS) systems that support power management, control and monitoring systems during the transition to emergency power, particularly on modern vessels with advanced power management systems (PMS), where several UPS units may be installed. Batteries should be properly maintained and replaced before degradation affects capacity or performance. On PMS-controlled ships, a reliable UPS supply is critical for blackout recovery, as loss of UPS power can disrupt control and monitoring functions and delay restoration of emergency power.
While realistic testing of emergency power systems is essential, preventing blackouts remains the first line of defence. Operators should also refer to Gard’s previous insight, The importance of blackout awareness and prevention, for further guidance.
Source: GARD
Related News.
October 15, 2026
Hong Kong Global Maritime Trade Summit to return for third edition
The International Chamber of Shipping, in collaboration with the Transport and Logistics Bureau of the Government of Hong Kong and the Hong Kong…
October 15, 2026
Appetite for US crude oil exports climbs despite high freight
South Korea tops US crude destinations at 568,600 b/d VLCC rates to Asia double, closing arbitrage window European refining margins…
October 15, 2026
Shipping stocks Rally as Hormuz Traffic plunges 75%
Ship traffic through the Strait of Hormuz — a critical chokepoint handling about 20% of global crude oil and liquefied natural gas shipments — has…
October 15, 2026
Diana Shipping announces Time Charter Contract for m/v G P Zafirakis with Classic Maritime
Diana Shipping, a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
October 15, 2026
New IMO ESP Code framework for Remote Inspection Techniques
The International Maritime Organisation, through Resolution MSC.584(111) , has adopted amendments to the International Code on the Enhanced…
October 15, 2026
ABS opens Offshore & Marine Support Center in Bergen
ABS has expanded its capabilities in the Norwegian maritime market with the opening of a cutting-edge support center in Bergen, bringing advanced…
October 15, 2026
MOL holds giant step memorial ceremony and beach cleanup at Kashima Coast
Memorial and Reflection 20 Years After the Accident: Learning from the Past to Foster an Even Stronger Safety Culture Mitsui O.S.K. Lines, announced…
October 15, 2026
KEZAD-based Arabian Gulf Steel Industries achieves lowest verified Carbon Footprint for Rebar
CARES UK verified Environmental Product Declaration confirms 139 kg CO₂e per tonne for rebar produced at AGSI’s KEZAD Abu Dhabi facility Arabian…
October 15, 2026
Indian Register of Shipping announces launch of first fleet support ship INS Surya
Indian Register of Shipping continues to strengthen its role in supporting the Indian Navy and India’s naval shipbuilding capabilities through the…
October 15, 2026
VLCCs Climbing the Record Charts
LR2 The TC1 75kt MEG/Japan index decreased by only a single point this week to WS928. The corresponding Baltic round-trip TCE fell by $2,000 to…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved