JSI Alliance delivers safe and efficient heavy-lift installation for Dahej berth expansion

The JSI Alliance is proud to have successfully completed a major project in India for client Afcons Infrastructure Limited. Afcons was contracted to construct a new liquid cargo berth for Gujarat Chemical Port . The JSI Alliance was contracted for the execution of critical heavy lifting operations for the development.

Complex and challenging environment
The project scope was complex, requiring extensive heavy-lift capabilities for the installation of eight jackets and fifteen berthing dolphins weighing between 500 and 600 t, at an outreach of 10 m.
Work took place in an extremely challenging environment. The location is subject to a 10 m tidal rise, resulting in currents of up to 5 kn. To compound matters, the seabed is comprised of sand, rendering many conventional mooring solutions unsuitable.
A further factor was that the location was operational at the time of installation – all activities had to be undertaken without interrupting two live, frequently used berths. This resulted in severe space restrictions, leading to further mooring complexities.

Tailored solution
Calling upon the expertise of a wide range of internal disciplines, the JSI Alliance developed a solution fully aligned with the requirements of the project. The Alliance mobilised the heavy-lift vessel (HLV) Jumbo Javelin.
The heavy-lift vessel enabled safe and efficient execution by providing a single platform for the transport and installation of prefabricated structures. Mobilisation commenced on 3 November and took place over a period of fifteen days. During this time, the JSI Alliance equipped the Jumbo Javelin with a flyjib that enabled her to perform the necessary lifting scope.

Heavy-duty mooring solution
The vessel was also outfitted with an eight-point mooring spread tailored to the seabed and tidal conditions of the project location. Creating sufficient holding force in such a
restricted area required utilisation of 17 t anchors and 64 and 52 mm mooring lines with a Minimum Breaking Load of approximately 300 t per line.
The Jumbo Javelin was equipped with custom-made 250 t winches. It was determined that eight, in place of four, winches should be installed to provide a back-up wire, ensuring safety and redundancy.
Significant forces
To absorb the significant forces involved, it was necessary to strengthen the vessel with additional steel. Installation of the spread called upon anchor handling support vessels with sufficient capacity for the heavy-duty components employed. The vessels were required to perform the mooring installation during a four-hour tidal window, when the current was at its lowest speed.
Once connected to the mooring spread, the Jumbo Javelin remained in position for several days at a time, thereby avoiding interruption to berthing operations.

Efficient demobilisation and discharge
The first loadout commenced on 3 December at Dighi Port. In total, the Jumbo Javelin made six voyages. The last item was installed on 14 March, before the vessel departed for Dighi Port for demobilisation, which took place over just seven and a half days. Following this, the Jumbo Javelin sailed on to Singapore to return equipment to suppliers. Discharge was completed in two days and, on 6 April, the project was fully completed.
Robert de Waard, Project Manager at the JSI Alliance, said, “The successful completion of this project is a testament to the teamwork, expertise and commitment of everyone involved. By drawing on the shared resources and capabilities of the JSI Alliance, we were able to develop a solution tailored to the complex site conditions and deliver the project safely and efficiently.
“I would like to thank all those involved for their efforts, including my colleagues from all departments, as well as our suppliers, including Franklin Offshore International and Mooreast Asia, for their support with the anchor handling equipment. I would also like to extend my appreciation to Seacontractors, who supported Afcons with the provision of two vessels for anchor handling and contributed to the successful execution of the project.
“Of course, we are also extremely grateful to Afcons for placing its trust in the JSI Alliance. Our two teams have worked together closely throughout the project, with Afcons being involved, and providing expert guidance, in all aspects. We have enjoyed the collaboration and look forward to working together again in the future.”
Related News.
September 4, 2026
QatarEnergy extends LNG cancellations into November as Hormuz disruption drags on
QatarEnergy’s latest cancellations run into early November. Buyers in Europe and Asia are finding replacement cargoes, switching to other fuels or…
September 4, 2026
Shipping must pool demand to unlock alternative fuel investment, says EmissionLink
Shipping must move beyond individual fuel procurement strategies and aggregate demand for alternative fuels if it is to unlock the investment needed…
September 4, 2026
EuroHoldings announces Charter Contract Extensions for two of its Feeder Containerships, M/V Joanna and M/V Aegean Express
Euroholdings, an owner and operator of container carriers and tanker vessels and provider of container and tanker seaborne transportation…
September 4, 2026
Titan and Sogestran agree long-term partnership for new 6,000cbm LNG bunker vessel
Agreement covers the construction, charter and operation of the vessel in the Western Mediterranean. Titan Clean Fuels, part of Molgas Group, has…
September 4, 2026
Piraeus Port Authority provides practical support to the Municipality of Salamina for the restoration of recent wildfire affected areas
Immediate response by Piraeus Port Authority through the provision of an excavator to support the removal and collection of fire-damaged materials…
September 4, 2026
Trump vows US will take ‘all’ of Venezuela’s oil as deal details emerge
The White House has published the terms of its Venezuela oil deal, naming the private company at its centre and confirming Washington’s majority…
September 4, 2026
SSA Marine upgrades benefit shippers as air draft project enters final months
Following the completion of a more than $100 million modernization project, SSA Marine is expanding capacity and improving efficiency at its…
September 4, 2026
Lloyd’s Register launches RouteFlex to provide unprecedented stowage flexibility for container operators
New LR RouteFlex application leverages metocean data to empower operators with more flexible, dynamic, voyage-based stowage optimisation. Lloyd’s…
September 4, 2026
“Deeper Than It Seems”an awareness campaign revealing the regulatory work behind every coastal tourism experience
The Saudi Red Sea Authority has launched its awareness campaign "Deeper Than It Seems," introducing the regulatory system that underpins maritime and…
September 4, 2026
Intermodal Report Week 35 2026
Pls find below the Intermodal Report - Week 35 2026 Intermodal Report Week 35 2026
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved























