Neptun Deep progress: pipelaying kicks off in the Black Sea

- Length of the pipeline bringing gas ashore: 160 km
- The first of the pipe-laying vessels, the Castoro 10, has arrived in Romania
OMV Petrom, the largest integrated energy producer in South-Eastern Europe, and SNGN ROMGAZ SA, the largest producer and main supplier of natural gas in Romania, announce the start of construction works on the offshore pipeline that will transport gas from offshore to shore, marking an important step forward in the Neptun Deep project.
“Neptun Deep is a strategic project for Romania and for the energy security of the region, involving investments of around EUR 4 billion and an estimated annual production of around 8 billion cubic meters of natural gas. In 2026, we will make significant progress here in Romania: installing the offshore pipeline, subsea equipment, and the production platform. All activities are carried out to the highest safety and quality standards, with the objective of starting production in 2027,” said Christina Verchere, CEO of OMV Petrom.
“The installation work planned for this year involves mobilizing a fleet of approximately 50 vessels – up to 10 of which are involved in the pipeline installation work. These are world-class vessels specialized in subsea installations, including some of the largest offshore units in the world. The integration of maritime, subsea, and onshore operations is essential to delivering the project safely and within an ambitious timeframe,” said Cristian Hubati, the OMV Petrom Executive Board responsible for Exploration and Production.
”The main gas pipeline installation kick-off represents an essential milestone in the development of Neptun Deep project. The existing partnership demonstrates efficient cooperation for delivering such a complex project, with a key role in energy security. The completion of the investment and start of commercial production from the natural gas fields, with first gas delivery in 2027 will strengthen Romania’s position by an energy resilience advantage at national and regional level,” stated SNGN ROMGAZ SA CEO Răzvan Popescu.
”Within Neptun Deep project, the main gas pipeline will be part of the gas production infrastructure. During this year, the project is transitioning from a global to a local execution dimension, with a large mobilization of resources for the installation and connection of subsea equipment in the Black Sea. We are determined to successfully complete this project, conduct the offshore operations safely, through the joint efforts of the project teams and contractors involved in the Neptun Deep project,” stated SNGN ROMGAZ SA Deputy CEO Aristotel Jude.
The first vessel in the fleet required for the Neptun Deep project has arrived in Romania: Castoro 10 will install the first section of the pipeline in the coastal area. The connection will be made via the microtunnel already constructed in Tuzla, a technology that enhances work safety and minimizes environmental impact.
The 160-km pipeline – a key component of the offshore infrastructure
The pipeline installation phase is a key component within the project. The pipeline will stretch over approximatively 160 km, built from thousands of steel pipe segments with a diameter of 30” (76 cm).
The pipeline will transport natural gas from the offshore production platform to shore, where it will be metered and delivered to the National Transmission System.
The Neptun Deep infrastructure includes the offshore production platform, 3 subsea systems, 10 production wells – four already drilled on Pelican South and six underway on Domino – as well as the onshore gas metering and control station at Tuzla.
Pipeline installation vessels operate as miniature assembly lines. The pipeline joints are aligned, welded together, tested and coated on board, before being lowered in a continuous string to the seabed. This system enables rigorous quality control at each step and high operational efficiency even in offshore conditions.
Key vessels involved in the installation activities:
- Castoro 10 – a specialized pipe-lay vessel for nearshore installation, over 160 metres in length
- Castorone – one of the largest and most powerful offshore pipelayers globally, approximately 330 meters length
- JSD 6000 – one of the most advanced multipurpose deep‑water pipelaying and heavy‑lift vessels currently in service. It will carry out the installation of the subsea infrastructure in the deep‑water area, ensuring the connection of the wells to the production platform.
These vessels will be supported by supply vessels, tugboats, barges and ROV-operated units ensuring efficient and safe offshore operations.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved