Port Houston completes its portion of Project 11 Dredging

Improves Safe, Efficient Two-Way Vessel Movement in the Houston Ship Channel through Galveston Bay
Port Houston, working in partnership with the U.S. Army Corps of Engineers (USACE), has completed its portion of the Houston Ship Channel Expansion – Project 11, a historic milestone in the future safety, efficiency, and competitiveness of the busiest waterway in the United States. Construction of channel improvements began in 2022, and now the project has reached its most important milestone – dredging completion of the widening of the Galveston Bay reach from Bolivar Roads to Morgans Point. With this work done, Port Houston-led project dredging of the Houston Ship Channel is complete.
Widening of the channel through Galveston Bay, from 530 feet to 700 feet, represents a physical transformation that allows for improved safety, greater efficiency, and increased economic benefit of this critical economic artery of the region, state, and nation. As vessels continue to grow in length, beam, and tonnage across a variety of vessel types, the widened Galveston Bay reach will help keep the facilities relying on the channel competitive and dynamic, both today and into the future.
Port Commission Chairman Ric Campo said, “We commend the incredible Port Houston team, our bipartisan federal and local delegations, and our industry and federal partners for their collaboration and capacity to see clearly the importance of this vital gateway to our nation and ensure its ability to safely sustain and grow international trade. This collaborative achievement is truly a testament to the hard work of all the individuals involved in the project and reminds us of the importance of the Houston Ship Channel to the nation.”
While Port-led dredging is now complete for navigation, some beneficial use aspects of the project remain under construction, including marsh areas that are being built with dredged material. To the extent possible, all Project 11 dredged material in the Galveston Bay area was used to construct environmental features, which will ultimately include approximately 10 acres of bird islands, 276 acres of marsh, and 324 acres of oyster reefs. In addition to these environmental benefits, Project 11 channel expansion is expected to provide air quality benefits, as vessel nitrogen oxide emissions are expected to be reduced by between three percent and seven percent. In addition, the dredges contracted for the first three segments of the project were equipped with either Tier 3 or Tier 4 engines or scrubbers, which efficiently remove pollutants from exhaust gases.
The 52-mile-long Houston Ship Channel serves more than 200 private facilities and eight public terminals, in industries from petrochemicals and heavy machinery to consumer goods and energy. In a report released earlier this year, the USACE recognized the channel as the busiest waterway in the United States, handling approximately 12% of the nation’s total waterborne tonnage. In fact, the Houston Ship Channel supports 3.37 million jobs nationwide and generates $906 billion in annual economic activity in the United States according to a 2022 third-party economic impact study.
Project 11 is expected to generate massive additional economic benefits to the region. A draft study by the Perryman Group estimates that by 2040, Segment 1 of Project 11 alone will generate $60.95 billion in statewide economic benefit and add 440,665 jobs in Texas. Port Houston anticipates publishing the study when it is finalized.
Based on Project 11 improvements and the experience gained through multiple research initiatives and full mission bridge simulations, the Houston Pilots have revised their Navigation Safety Guidelines. These revisions are expected to deliver measurable efficiency gains for all users of the Houston Ship Channel – including LPG carriers, oil and product tankers, bulkers, and container ships.
Among the key benefits, daylight restrictions have been extended by up to two and a half hours in each direction, allowing for more time for two-way vessel movements along the waterway and improving flexibility for both inbound and outbound scheduling. These enhancements not only increase the operational efficiency of individual vessels but also create system-wide benefits by smoothing vessel traffic across a broader time window. As a result, harbor assist tug and dock operations are expected to experience greater predictability, reduced congestion, and improved asset utilization.
Earlier project phases also allowed the Pilots to increase the permissible size of container ships calling at Bayport Container Terminal. Today, vessels between 15,000 and 17,000 TEU – matching the capacity of the Panama Canal – can now safely call Bayport. This milestone, combined with continued Pilot experience handling larger vessels in the improved channel, marks another important step toward realizing the shared vision of a true 24-hour port – one that enhances safety, reliability, and efficiency for every stakeholder on the Houston Ship Channel.
The planning of Project 11 began in 2010, when Port Houston leadership, working with Congress and the USACE, recognized the need to widen and deepen the channel to more safely and efficiently accommodate the growth in the size of vessels transiting it. In the years since then, the Port Houston team accelerated the project by working in parallel versus typical sequential steps related to specific federal authorizations. The result: this project and its benefits are being realized sooner than typical for almost any project of this scope.
The Houston Ship Channel Expansion – Project 11 has been honored with multiple awards, including the 2025 Environmental Excellence Award from the Western Dredging Association (WEDA) and the 2025 Texas American Society of Civil Engineers (ASCE) Outstanding Civil Engineering Achievement Award (OCEA).
The USACE will lead the remaining portions of the project, which are scheduled to be completed in 2029 and will generate further benefits along the channel. More details on the massive expansion, including an interactive map, can be found here: https://www.expandthehoustonshipchannel.com/.
Source: BUSINESS WIRE
Related News.
October 30, 2026
European Shipowners call on MEPs to back Commission proposal to include two Indian yards in the EU ship recycling list
The Environment Committee of the European Parliament votes on 4 November on a motion for resolution objecting to the Commission’s proposal to add two…
October 30, 2026
Oversea signs commercial agreement with UECC following Successful Pilot
Following a successful pilot onboard Auto Advance, UECC has chosen to enter into a commercial agreement with Oversea. The pilot demonstrates how…
October 30, 2026
First NABEP Crude Cargo Under U.S. Agreement Arrives in Texas
Shipment of 1 million barrels arrived as NABEP production passes 223,000 barrels of oil equivalent per day. Two tankers carrying 1 million barrels of…
October 30, 2026
LNG carrier prices fall to $245 million, threatening Korean Shipbuilders’ Margins
Prices for high-value vessels, including liquefied natural gas carriers and ultra-large container ships, have begun to decline despite rising…
October 30, 2026
Vehicle Carrier Safety Forum publishes new Fire Drill Guidelines for vehicle carrying vessels
The Vehicle Carrier Safety Forum has published new Fire Drill Guidelines for Vehicle Carrying Vessels, providing vessel operators with a practical…
October 30, 2026
Is an Atlantic Basin crude glut on the cards?
Atlantic crude discounts fail to offset high freight to Asia, raising the risk of a regional glut as VLCC availability tightens. Freight…
October 30, 2026
The future of trade infrastructure in Europe is connectivity
One year after its inauguration, Rijeka Gateway offers a glimpse into the future of European trade. On 10 September last year,…
October 30, 2026
Allied – Weekly Market Review – Week 43
Please find below the Allied Weekly Report for Week 43 | 2026 ALLIED - Weekly Market Report- Week 43
October 30, 2026
Intermodal Report – Week 43 2026
Please find below the Intermodal market report for week 43 2026. Intermodal Report Week 43 2026
October 30, 2026
Wind Challenger-Equipped LNG Dual-Fueled Coal Carrier ‘MAIZURU KAZENOMAI’ Delivered
-While Supporting a Stable Energy Supply, Reducing Environmental Impact - Mitsui O.S.K. Lines announced the delivery and entry into service of an…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved