Van Oord completes ballasting operations and scour protection for the West White Rose project

Van Oord has successfully completed high-precision ballasting operations for the West White Rose project in Canada. Van Oord deployed its flexible fallpipe vessels Nordnes and Stornes to carry out the work. In addition, Van Oord installed a protective scour edge around the Concrete Gravity Structure to mitigate the effects of seabed erosion.
Located in the Jeanne d’Arc Basin, approximately 350 kilometres off the east coast of Newfoundland, Canada, the West White Rose project is an expansion of the White Rose field. It consists of a fixed drilling platform situated on a custom-designed Concrete Gravity Structure (CGS). The CGS has a base diameter of 122 metres, is 145 metres tall, and supports an integrated drilling and production topside. Van Oord’s scope of work is divided into four phases: seabed preparation, solid ballasting activities, scour protection, and flowline protection.
Seabed preparation layer
During the first phase, completed in September 2024, Van Oord installed a seabed preparation layer that serves as the foundation for the CGS. The installation required strict adherence to client specifications and involved extensive planning, material testing, rigorous quality control of quarried rock, full-scale trials, and the expertise of a highly qualified and committed project team, along with the vessel crew of Stornes, which was deployed for the task.
Ballasting operations
In the second phase of the project, Van Oord carried out solid ballasting of the CGS to ensure sufficient weight for seabed stability once positioned. The unique design of the structure required a high degree of accuracy. Van Oord’s flexible fallpipe vessels Nordnes and Stornes approached the CGS simultaneously using dynamic positioning (DP), with one vessel on each side. Using boom belt-conveyors, they inserted MagnaDense (iron ore) into the CGS’s outer ring compartments. The vessels were constantly positioned 180 degrees from each other while moving around the CGS to fill all 24 compartments evenly. The ballasting operations were meant to prepare the CGS before its tow-out. The CGS has now been positioned on top of the seabed preparation layer previously installed by Van Oord.
’Van Oord has proven that it can execute a project of this complexity according to the highest standards. It has been successful thanks to excellent collaboration with both our client and across the entire team, as well as our skilled people and our fantastic equipment and automation.’
Hans Smit, Project Manager at Van Oord
Scour and flowline protection
In the third phase of the project, Van Oord deployed its flexible fallpipe vessel Nordnes to install a protective scour edge around the CGS. The final phase, scheduled for Q4, will involve stabilising the pipelines from the drilling platform on the seabed. Once completed, the client will be able to bring the platform into operation.
Related News.
October 16, 2026
Navigating the Multi-Orbit Era: In Conversation with Intellian’s Jon Harrison at SMM 2026
At SMM 2026 in Hamburg, the rapid evolution of maritime satellite communications took centre stage. Across the exhibition halls, discussions among…
October 16, 2026
Cyprus ports need joint energy and investment strategy, shipping agents chief says
Cyprus needs a coordinated strategy for shipping, energy and environmental protection to support port investment and modernisation, Cyprus shipping…
October 16, 2026
MASO Public Affairs introduces MASO Regulatory Intelligence
A new subscription service helping businesses understand what is changing and what it means for them MASO Public Affairs introduces MASO Regulatory…
October 16, 2026
Anglo-Eastern helps turn CMBTECH’s ammonia ambition into an operational reality
From early feasibility study and risk-based design to newbuilding supervision, crew readiness and technical management, Anglo-Eastern drew on its…
October 16, 2026
Escalation of attacks threatens to derail recovery in Middle East oil exports
World oil demand is forecast to fall by 2.5 mb/d y-o-y in 4Q26 and 2.6 mb/d on average in 2026. As the Iran war manifests itself through restricted…
October 16, 2026
New study finds shipping pays twice its share to EU ETS earmarked revenues should triple to help build market for sustainable fuels and technologies
Shipping is responsible for around 10% of EU ETS emissions but pays almost 20% of the ETS bill. Unlike other sectors, it has never received free…
October 16, 2026
MSARC strengthens maritime mass rescue readiness through training and national live exercise off Dakar, Senegal
Joint MSARC–FHAS programme combines three days of SAR training with a national multi-agency live exercise The Maritime Search and Rescue Council ,…
October 16, 2026
Sogese report deliveries are still being delayed as container freight rates fluctuate
FOR IMPORTERS Spot rates into the Mediterranean are back at January levels, Far East to Europe reliability sits at pandemic lows, and nearly…
October 16, 2026
Glencore begins trading on Australian Securities Exchange
Glencore has begun trading on the Australian Securities Exchange under the ASX code GLC. Gary Nagle, Glencore’s CEO, said it was an exciting day for…
October 16, 2026
BIMCO Shipping Number of the Week
Suez Canal container ship transits exceed 50% of pre-disruption levels "During the first two weeks of October, weekly container ship capacity…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved