Van Oord completes ballasting operations and scour protection for the West White Rose project

Van Oord has successfully completed high-precision ballasting operations for the West White Rose project in Canada. Van Oord deployed its flexible fallpipe vessels Nordnes and Stornes to carry out the work. In addition, Van Oord installed a protective scour edge around the Concrete Gravity Structure to mitigate the effects of seabed erosion.
Located in the Jeanne d’Arc Basin, approximately 350 kilometres off the east coast of Newfoundland, Canada, the West White Rose project is an expansion of the White Rose field. It consists of a fixed drilling platform situated on a custom-designed Concrete Gravity Structure (CGS). The CGS has a base diameter of 122 metres, is 145 metres tall, and supports an integrated drilling and production topside. Van Oord’s scope of work is divided into four phases: seabed preparation, solid ballasting activities, scour protection, and flowline protection.
Seabed preparation layer
During the first phase, completed in September 2024, Van Oord installed a seabed preparation layer that serves as the foundation for the CGS. The installation required strict adherence to client specifications and involved extensive planning, material testing, rigorous quality control of quarried rock, full-scale trials, and the expertise of a highly qualified and committed project team, along with the vessel crew of Stornes, which was deployed for the task.
Ballasting operations
In the second phase of the project, Van Oord carried out solid ballasting of the CGS to ensure sufficient weight for seabed stability once positioned. The unique design of the structure required a high degree of accuracy. Van Oord’s flexible fallpipe vessels Nordnes and Stornes approached the CGS simultaneously using dynamic positioning (DP), with one vessel on each side. Using boom belt-conveyors, they inserted MagnaDense (iron ore) into the CGS’s outer ring compartments. The vessels were constantly positioned 180 degrees from each other while moving around the CGS to fill all 24 compartments evenly. The ballasting operations were meant to prepare the CGS before its tow-out. The CGS has now been positioned on top of the seabed preparation layer previously installed by Van Oord.
’Van Oord has proven that it can execute a project of this complexity according to the highest standards. It has been successful thanks to excellent collaboration with both our client and across the entire team, as well as our skilled people and our fantastic equipment and automation.’
Hans Smit, Project Manager at Van Oord
Scour and flowline protection
In the third phase of the project, Van Oord deployed its flexible fallpipe vessel Nordnes to install a protective scour edge around the CGS. The final phase, scheduled for Q4, will involve stabilising the pipelines from the drilling platform on the seabed. Once completed, the client will be able to bring the platform into operation.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved