Nexans completes critical repair of Estlink 2 subsea interconnector between Finland and Estonia

Nexans, a global leader in the design and manufacturing of cable systems and services, specializing in the offshore wind sector and subsea interconnectors, has completed the repair of the Estlink 2 interconnector under contract for Fingrid, Finland’s transmission system operator. The successful operation reinstates one of the Baltic region’s most important electricity links.
The interconnector was damaged in December 2024, prompting an urgent need for investigation and repair. Nexans began supporting Fingrid immediately—mobilizing its dedicated IMR and engineering teams early in 2025. The offshore repair operation was executed in May.
A specially equipped vessel was rapidly mobilized, carrying a full spread of jointing equipment, test tools, and spare materials—including critical stock transferred from Fingrid’s depots to Nexans’ facility in Halden, Norway. All components were thoroughly reviewed and tested to ensure readiness. The offshore campaign, which involved replacing a one-kilometer section of cable, was completed safely and on schedule—with full alignment between Nexans’ technical execution and Fingrid’s operational requirements.
“This successful repair demonstrates our readiness and capability to respond fast and deliver—where it matters most,” said Pascal Radue, EVP of Nexans’ Power Transmission Business Group. “Nexans leads the world in high-voltage subsea IMR because we combine deep technical expertise with operational discipline, integrated systems thinking, and a track record of execution. From planning to offshore jointing, we know what it takes to get critical infrastructure back online—safely, reliably, and on time.”
“We appreciate Nexans’ strong commitment and technical expertise throughout the planning and execution of this repair,” said Kimmo Nepola, Unit Manager at Fingrid. “The interconnector plays a key role in maintaining security of supply and energy cooperation in the region. Together, we’ve ensured that Estlink 2 can return to operation safely and on schedule.”
The Estlink 2 interconnector enables electricity exchange between Finland and Estonia and plays a vital role in regional energy integration. Commissioned in 2014, the 650 MW link includes 145 kilometers of subsea cable manufactured by Nexans.
This project further underlines Nexans’ strategic focus on IMR services—ensuring the reliability, resilience, and security of subsea cable infrastructure as demand for clean and interconnected energy systems grows globally.
Related News.
November 27, 2026
Intelligent Skies, Secure Seas: Navigating Connectivity, Cyber Resilience, and AI Liability at the 5th CSN Greece ICT Conference
The 5th CSN Greece ICT Conference, held on 19th November 2026 at the Ploes Floating Venue in Paleo Faliro, Athens, successfully convened maritime…
November 27, 2026
EU moves to ban tankers insured in Russia, repair services at Russian refineries
EU targets Russian-insured tankers, refineries Von der Leyen announces 22nd sanctions package All 27 member states must approve new…
November 27, 2026
IMO tackling fraudulent registries together
Strong national systems and international information sharing are crucial to tackling fraudulent registries and fraudulent ship registration…
November 27, 2026
Open letter on freedom of navigation and the protection of seafarers
Dear High Representative Kallas, Dear Foreign Affairs Ministers, European Shipowners | ECSA, BIMCO, the Cruise Lines International Association…
November 27, 2026
Davies Turner warns of Rising Asia-UK Container Disruption and European Port Congestion
Davies Turner, one of the UK’s largest independent freight forwarding and logistics companies, says that disruption to container shipments from Asia…
November 27, 2026
Disruptions still dominate tanker market outlook
"This year, tanker markets have been affected by disruption to transits through the Strait of Hormuz, the Houthi blockade of Saudi Arabian Red Sea…
November 27, 2026
Panama’s President called on to match COP31 Heroism with action at shipping climate talks
As a series of crucial meetings tasked with cutting greenhouse gas emissions from global shipping takes place this week and next, environmental NGOs…
November 27, 2026
Trafigura appoints Helio Cumbi as Executive Director, Mozambique
Trafigura has appointed Helio Cumbi as Executive Director, Mozambique, and Business Development Lead for East and Southern Africa Oil. Helio is a…
November 27, 2026
“K” LINE holds FY2026 Global Dry Bulk Meeting
Kawasaki Kisen Kaisha, announces that it held a global meeting for its dry bulk business at the company’s head office on November 9 and 10. The…
November 27, 2026
MOL launches ‘AQuA’ safety and quality improvement initiative
Standardizing Group-wide Safety and Quality Assessment Criteria to Enhance Vessel Safety and Quality Mitsui O.S.K. Lines, announced the launch of…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved