Tiel-Waardenburg dyke reinforcement large-scale sustainable construction is feasible

Implementation of the Tiel-Waardenburg dyke reinforcement started in 2023. Consortium Mekante Diek (Ploegam, Van Oord, Dura Vermeer) is carrying out this dyke reinforcement commissioned by Rivierenland Water Board. It is the first large-scale construction project in the Netherlands to be completed using almost entirely electric equipment. Research institute TNO examined the efficiency and sustainability impact of this project over the past two years.
Rivierenland Water Board challenged the market with the 2020 tender to achieve the greatest possible emission reduction. Mekante Diek responded by carrying out the dyke reinforcement project largely emission-free, using some forty machines with mostly interchangeable, rechargeable battery packs, such as trucks, tractors, cranes, asphalt sets and piling rigs. The consortium also created WattHub, Europe’s first XL fast charging plaza, together with partner Betuwewind. The charging plaza, situated next to the dyke reinforcement site, is powered by renewable electricity, specifically designed for trucks and heavy equipment, and is accessible to all.
Conclusion: Implementing large-scale construction projects in a sustainable way is possible
Mekante Diek commissioned TNO to study the efficiency and sustainability impact of zero emission equipment and the WattHub charging plaza. Zero emission equipment was compared with conventional diesel equipment in various age categories. The results underline that large-scale emission-free construction is possible. The project saves over 1,190 tonnes of CO₂ and 3,260 kg of nitrogen (NOx) per year, equivalent to what 59,500 trees can absorb in a year. 100% green electricity is used to charge the equipment, 90% of which comes directly from wind turbines, preventing grid congestion. TNO’s research shows that great strides have been made, but there is still room for improvement. For example, in charging schedules and energy consumption.
TNO’s report, ‘Assessment of sustainable charging operations of Mekante Diek’s construction equipment’ can be downloaded from the digital visitor centre.
‘During the tender, Mekante Diek met our goals and ambition in an appealing way with maximum commitment to zero emission implementation. This exceeded our expectations. Demonstrating entrepreneurship in deploying zero emission equipment on this project has helped accelerate the transition to zero emission construction.’
Details of Tiel-Waardenburg dyke reinforcement
The Tiel-Waardenburg dyke reinforcement is part of the national Flood Protection Programme (HWBP), the largest dyke reinforcement operation since the Delta Works. The Waal dyke between Tiel and Waardenburg will be raised, widened and fitted with more than nine kilometres of sheet piling over a distance of about twenty kilometres. The project will be completed while people live, do business and relax around the dyke, and the project borders a Natura2000 area. Work is well on track. Seven km of sheet piling has been installed and 4.7 km of the dyke has now been protected against flooding. By 2027, the entire dyke must be protected against flooding.
Related News.
October 19, 2026
OL Shipping Group in Tokyo: Capt. Eberhard Koch calls for realistic solutions to Maritime Decarbonisation
An intensive and engaging couple of days in Tokyo brought together leading figures from the international maritime community, providing a valuable…
October 19, 2026
Regatta for Peace one of the largest ever in Cyprus
Cyprus will host the first European stop on a global sailing journey leading up to the 2027 America’s Cup in Naples. More than 120 sailors…
October 19, 2026
The propulsion technology powering the marine energy transition
The marine industry is under increasing pressure to future-proof fleets, balancing the need to reduce emissions and improve efficiency. Propulsion…
October 19, 2026
Signal Ocean acquires Lgmar
Signal Ocean announced the acquisition of Lgmar, the Athens-based company behind Telix, a maritime email and communication platform in daily use…
October 19, 2026
Canada clean power push challenged by interprovincial grid limits, says GlobalData
Canada is entering a pivotal phase of power-sector expansion as federal tax credits, the phase-out of coal-fired generation, and accelerating…
October 19, 2026
Maritime safety depends on human factors and leadership, not procedures alone
Interim survey findings point to a gap between seafarers’ perceptions of risk and injury data Seafarers may misjudge when and where they are most at…
October 19, 2026
New BIMCO contracts tackle ship recycling and energy-saving retrofits
BIMCO adopted two new contractual solutions designed to help you manage important operational and regulatory challenges: the revised…
October 19, 2026
Stena Line to acquire vessel and make changes to its network
Stena Line has reached an agreement to acquire the RoRo vessel Somerset from CLdN. Subject to closure and transfer, the vessel would begin operating…
October 19, 2026
DORIC WEEKLY INSIGHT 16 OCTOBER 2026
Please find below the DORIC Market Insight for the week ending 16th October 2026. Weekly Report 16.10.2026
October 19, 2026
Important information for port clients and freight carriers effective November 1, a new traffic overpass and port checkpoint will open for traffic to the Port of Riga on Kundziņsala
Starting November 1 of this year, a new traffic overpass connecting Tvaika Street to Kundziņsala will open to facilitate traffic to and from the Port…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved