Deferred well P&A could add $5.5bn to UK decommissioning bill by Westwood

Political and fiscal uncertainty has undermined investor confidence in the UK oil and gas industry. Production is in decline, progression of new field developments has stalled, and exploration activity is at an all-time low. 22 fields ceased production in 2024 and 40% of fields that are currently producing or under development could cease economic production before 2030, based on current firm investment plans. A similar number could cease between 2030 and 2035. Decommissioning activity should be ramping up, because over the next 10 years more than US$26 billion could be spent on decommissioning in the UK.
Well plug and abandonment (P&A) activity accounts for approximately 50% of decommissioning spend, therefore the UK offshore drilling rig market would be expected to be in a buoyant state with a healthy backlog of work.
Westwood has evaluated the outstanding and future well P&A activities in relation to the cessation of production (CoP) year for fields, specifically for wells that require a semisubmersible or jackup unit for the activities (Figure 1). At the end of 2024, 483 wellbores require abandonment activities which will need drilling rigs. Assuming mid-case P&A durations, based on NSTA benchmarking, this equates to 70 years of P&A work. The NSTA guidance is for P&A activities to be completed within two years of CoP or a maximum of five, however, 73 of these wellbores have had well P&A work outstanding for more than 10 years.
Westwood estimates that by the end of 2030, a further 420 wellbores will be added to the abandonment pool requiring rigs, equivalent to another 61 years of activity. This level of demand should in theory sustain rig utilisation dayrates in the near to mid-term for both jackups and semisubs. But P&A execution rates to date are lagging behind demand. There are only a limited number of rig contracts being awarded for P&A work. Of the 22 rigs (eight semisubs and 14 jackups) currently based in the UK, four are carrying out P&A work and three are stacked (two semisubs and one jack-up). There is a real risk of rigs moving overseas for contracts or rigs being retired. This would constrain future supply capability to meet the inevitable P&A requirements, which would inevitably lead to an increase in rig dayrates and other supply chain costs.
The impact of increasing service sector costs could have a significant impact on future P&A expenditure. For the wells expected to become inactive by end 2030, Westwood estimates that up to US$5.5 billon could be added to well P&A costs through cost inflation or execution inefficiencies. With the impact of decommissioning tax liabilities on abandonment expenditure, cost-effective P&A must be paramount.
There is sufficient P&A workscope to keep rigs, and the associated services, busy through to the mid-2030s in the UK, but contract awards are not aligning with available work. The longer well P&A work is delayed, the more wells are added to the outstanding work, which increases pressure on the supply chain, particularly rig demand, leading to increased costs. If companies continue to defer P&A activity, the uncertainty for the supply chain increases and this could be detrimental to the effective delivery of decommissioning in the UK.
Source: Westwood Energy
Related News.
October 19, 2026
OL Shipping Group in Tokyo: Capt. Eberhard Koch calls for realistic solutions to Maritime Decarbonisation
An intensive and engaging couple of days in Tokyo brought together leading figures from the international maritime community, providing a valuable…
October 19, 2026
Regatta for Peace one of the largest ever in Cyprus
Cyprus will host the first European stop on a global sailing journey leading up to the 2027 America’s Cup in Naples. More than 120 sailors…
October 19, 2026
The propulsion technology powering the marine energy transition
The marine industry is under increasing pressure to future-proof fleets, balancing the need to reduce emissions and improve efficiency. Propulsion…
October 19, 2026
Signal Ocean acquires Lgmar
Signal Ocean announced the acquisition of Lgmar, the Athens-based company behind Telix, a maritime email and communication platform in daily use…
October 19, 2026
Canada clean power push challenged by interprovincial grid limits, says GlobalData
Canada is entering a pivotal phase of power-sector expansion as federal tax credits, the phase-out of coal-fired generation, and accelerating…
October 19, 2026
Maritime safety depends on human factors and leadership, not procedures alone
Interim survey findings point to a gap between seafarers’ perceptions of risk and injury data Seafarers may misjudge when and where they are most at…
October 19, 2026
New BIMCO contracts tackle ship recycling and energy-saving retrofits
BIMCO adopted two new contractual solutions designed to help you manage important operational and regulatory challenges: the revised…
October 19, 2026
Stena Line to acquire vessel and make changes to its network
Stena Line has reached an agreement to acquire the RoRo vessel Somerset from CLdN. Subject to closure and transfer, the vessel would begin operating…
October 19, 2026
DORIC WEEKLY INSIGHT 16 OCTOBER 2026
Please find below the DORIC Market Insight for the week ending 16th October 2026. Weekly Report 16.10.2026
October 19, 2026
Important information for port clients and freight carriers effective November 1, a new traffic overpass and port checkpoint will open for traffic to the Port of Riga on Kundziņsala
Starting November 1 of this year, a new traffic overpass connecting Tvaika Street to Kundziņsala will open to facilitate traffic to and from the Port…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved