Wärtsilä will provide a 350 MW / 1474 MWh energy storage system for one of Australia’s largest energy providers

Technology group Wärtsilä has been contracted by EnergyAustralia to deliver 350 MW / 1474 MWh of capacity to the Wooreen Energy Storage System in Victoria, Australia. This pivotal project is set to enhance Australia’s infrastructure by providing essential grid stability and supporting the integration of renewable energy, aligning with the country’s ambitious decarbonisation goals. The scope of the contract includes engineering design, supply, commissioning, and a 15-year service agreement. The deal was booked in Q4, 2024.
The project was successful in the first round of the Capacity Investment Scheme (CIS), an Australian Government initiative to encourage new investment seeking to deliver 32 GW of renewable generation and dispatchable capacity by 2030. The site will be built adjacent to EnergyAustralia’s Jeeralang Power Station and become operational before the shut-down of the coal-fired Yallourn Power Station planned to retire in 2028. Construction will begin in 2025 and the WESS will be completed in 2027. Once operational, the system will provide energy to more than 230,000 homes for up to four hours at a time.
Recently, spot prices have surged due to colder weather, increased energy demand, and reduced renewable generation. This volatility in the energy market poses challenges for both consumers and providers. The energy storage project will provide EnergyAustralia with a natural hedge against such market fluctuations and help stabilise energy prices and ensure a more resilient energy supply.
“At EnergyAustralia, our purpose is to lead and accelerate the clean energy transformation for all,” said EnergyAustralia Managing Director, Mark Collette. “The Wooreen Energy Storage System is the largest single project investment made by EnergyAustralia. Wooreen will provide capacity to meet demand peaks while enabling more renewable energy to enter the electricity market, contributing to better customer energy outcomes.”
“This project is a landmark step for EnergyAustralia as they continue to decarbonise their asset portfolio while maintaining reliability for their customers,” said Andrew Tang, Vice President of Energy Storage & Optimisation at Wärtsilä Energy. “We are excited to partner on this significant project and help support their long-term energy goals. This project is Wärtsilä’s first in the state of Victoria and expands our footprint in Australia to 4.8 GWh across seven projects. Australia has already made great strides towards its decarbonisation targets, and this project will further boost its renewable energy capacity.”
The Wooreen energy storage system will utilise Wärtsilä’s Quantum High Energy technology and GEMS Digital Energy Platform, helping to secure Victoria’s energy supply and enabling more renewable energy to enter the electricity network while providing crucial grid services. The project is designed to switch to grid-forming mode, offering operational flexibility with faster response times to increase system stability and grid reliability while keeping energy prices low for consumers.
Today, Friday 28th of February, Wärtsilä representatives joined EnergyAustralia, Victorian Energy Minister, Lily D’Ambrosio, and other members of the Victorian Government at the Wooreen commencement ceremony.
Related News.
November 24, 2026
Greece has the most to lose from delays in shipping’s green transition, new analysis finds
UCL and WWF Greece report finds the IMO Net-Zero Framework offers Greek ship owners the clarity they need, and the best protection against a…
November 24, 2026
Snow Land joins Cool Carriers as the world’s first reefer with a gate rudder, a new chapter for sustainable and efficient reefer shipping
Cool Carriers, the world’s largest operator of specialised reefer vessels, took delivery of Snow Land from Kitanihon Shipbuilding in Japan on 12…
November 24, 2026
IBIA launches Marine Energy Outlook Survey as Annual Convention in New York
IBIA - The International Bunker Industry Association officially launched its Marine Energy Outlook Survey during the IBIA Annual Convention in New…
November 24, 2026
Why did ITF staff vote to strike again?
Staff at the International Transport Workers’ Federation (ITF) headquarters in London have voted to give their union a strike mandate. According to…
November 24, 2026
Nearly half of maritime crew tickets booked a week ahead are cancelled
Two new C Teleport reports show when maritime and aircrew teams book crew flights, how often they cancel, and what late booking costs, with a…
November 24, 2026
Kpler completes $1.5bn+ Sixth Street investment and continues accelerating growth
Investment backs Kpler's bold ambition to shape the future of global trade intelligence. Kpler, a leading provider of global physical trade…
November 24, 2026
How SAL and DNV are strengthening heavy-lift shipping
From classification and newbuilding support to operational tools and advisory expertise, SAL and DNV have been collaborating for decades. The…
November 24, 2026
PSA Singapore breaks ground on Tuas Port Phase Two to strengthen Global Trade Connectivity
PSA Singapore marked the groundbreaking of Tuas Port Phase Two, a significant step in the development of the world’s largest fully automated…
November 24, 2026
BIFA welcomes UK–EU trade progress and calls for clarity on implementation
The British International Freight Association (BIFA) has welcomed progress made at today's UK–EU Summit in Brussels, highlighting the potential…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved























…