Equinor reports on Norwegian development projects

Equinor is the operator of 19 projects currently under development in Norway. In the proposed National Budget for 2025, the Ministry of Energy listed the status of 13 Equinor-operated projects currently under development or recently completed.
The projects in question have a total investment framework of 198 billion kroner, from commencement to commissioning.
“Equinor has a good portfolio of profitable projects being developed in Norway, which will contribute to long-term security of supply of oil and gas to Europe. In 2023, our developments contributed to high activity and 25 billion kroner to the Norwegian supplier industry. Together with our partners and the industry, we have completed six projects during the past year,” says Trond Bokn, head of project development in Equinor.

The reported projects have seen a cost increase of 6.5 billion 2024-NOK over the past year, which is about 3 per cent. The overall increase since the plans for development and operation (PDOs) is 32.9 billion 2024-NOK. Currency effects account for 12.4 billion of this. If the Johan Castberg project and currency effects are omitted, the cost increase for the reported projects is around 3 percent since PDOs.
Two of the projects, Johan Castberg and Oseberg gas compression and partial electrification, have experienced a post-PDO increase of more than 20 percent, and are therefore mentioned specifically in the proposed national budget.
Johan Castberg
The production ship is now anchored at the field and Johan Castberg is on track for start-up towards the end of the year.
The cost increase in the project is 2.2 billion 2024-NOK since last year. This is due to a longer stay than estimated at Aker Solutions at Stord, currency effects and a general cost increase. Of this, almost NOK 800 million is currency effects. Since the PDO, estimated costs have grown by 25.7 billion 2024-NOK. Currency effects account for 8.1 billion of this.
Oseberg gas phase 2 and power from shore (OGP)
OGP is composed of partial electrification of the Oseberg Field Centre and Oseberg sør, as well as installation of a new compressor module at the field centre.
The cost increase over the past year is 1.2 billion 2024-NOK. Since the PDO, the cost increase is about NOK 2.5 billion in 2024-NOK. Since the PDO, estimated costs have grown by around 2.5 billion 2024-NOK. This is a result of longer delivery times for new transformers that were destroyed in a fire at Hitachi’s factory in Vaasa in 2023, as well as delays related to increased complexity. Planned commissioning has been postponed from 2026 to late 2027.
Snøhvit Future
Snøhvit Future encompasses onshore compression and electrification of Hammerfest LNG on Melkøya. Since the PDO, the cost increase is 1.9 billion 2024-NOK. More than 500 million of this relates to currency effects.
One of the main reasons for the higher costs is the joint venture’s decision to change the design of an electric boiler as a result of safety considerations.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved