Jan De Nul kicks off Orsted‘s Borkum Riffgrund 3 offshore wind farm construction

Jan De Nul Group’s heavy-lift vessel Les Alizés has installed the first of 83 monopile foundations at 53 kilometres off the island of Borkum. The foundations of Borkum Riffgrund 3 are up to 100 metres long and weigh up to 1,500 tonnes. They are manufactured by Steelwind in Nordenham and at Bladt Industries A/S’ Lindø plant in Denmark. Next year, a new generation of turbines, the SG 11.0-200 DD offshore wind turbine, will be installed on these foundations.
This installation campaign started immediately after the last monopile foundation for the Gode Wind 3 project (253 MW) was installed. In total, Les Alizés put 24 monopiles in place for the future turbines, including one monopile and topside of the offshore substation.
Peter De Pooter, Manager Offshore Renewables at Jan De Nul Group: “Our heavy-lift vessel, Les Alizés, has proven during the installation of the Gode Wind 3 foundations that she can handle the ever-larger monopile foundations for offshore wind farms. We look forward to continue working with Ørsted on Germany’s largest offshore wind farm to date.“
Jörg Kubitza, Managing Director of Ørsted in Germany: “With Borkum Riffgrund 3, we are setting new standards for our industry – both in terms of capacity and business model. The new project is the first offshore wind farm in Germany to be built that was awarded with a bid of 0 Euro per MWh in the offshore wind tenders. This enables us to directly support our corporate customers with their decarbonization. This is only possible on this scale using renewable energies through offshore wind energy.”
Borkum Riffgrund 3 will be built without an offshore substation.
Borkum Riffgrund 3 is the first Ørsted wind farm in Germany to be built without an offshore substation (OSS). The new connection concept, which is being implemented together with transmission system operator TenneT, provides a direct connection of the wind turbines via 66 kV export cables to the DolWin5 offshore converter platform from TenneT.
Together with Gode Wind 3, Borkum Riffgrund 3 will have a total capacity of more than 1.1 GW. This almost doubles Ørsted’s installed offshore wind power capacity in Germany to around 2.5 GW. The two wind farms are expected to be commissioned in 2024 and 2025 respectively.
Related News.
October 23, 2026
Columbia Group calls for greater focus on retaining women at sea as second She Beyond Conference takes place
Columbia Group has called on the maritime industry to create a future where women can thrive, progress and lead at sea, as it celebrated the second…
October 23, 2026
Neptune Group Welcomes “NIKOS TRAVLOS”
The new vessel proudly bears the name of Neptune's founder, who laid the foundation for the creation and enduring evolution of the Group. Her…
October 23, 2026
Wildcat Defense enters into exclusive agreement to acquire Fraser Shipyards
American family firm takes the next step in its strategy to rebuild U.S. shipbuilding and repair capacity, following its offer for Austal USA.…
October 23, 2026
Kawasaki signs strategic partnership MOU with Romania’s Transgaz for Onshore Hydrogen Gas Transport
Establishing a model for large-scale hydrogen supply and transport via pipelines Kawasaki Heavy Industries, announced at the Romania–Japan…
October 23, 2026
UK P&I Club and TT Club secure regulatory approval for Thomas Miller acquisition
The UK P&I Club and TT Club announce the successful completion of their joint acquisition of the Thomas Miller Holdings group, marking a major…
October 23, 2026
Valenciaport presents its Sandbox at PEIC’26 as a tool to bridge the gap between innovation and implementation
The opening session featured a discussion between Valenciaport President Mar Chao and Valenciaport Foundation Director Antonio Torregrosa. The…
October 23, 2026
Major investments strengthen Gothenburg RoRo Terminal
Expanded terminal areas, new rail connections and modernised quays are among the investments that have strengthened Gothenburg RoRo Terminal in…
October 23, 2026
ABP appoints key roles in the Humber
Associated British Ports has made two key appointments at its container terminals strengthening its unitised operations at the ports of Immingham…
October 23, 2026
Xinhua Silk Road 2026 North Bund Forum unveils 20 shipping-related achievements
The 2026 North Bund Forum opened in Shanghai on October 20 with 20 key shipping-related achievements spanning international cooperation, green…
October 23, 2026
Ports encouraged to prepare now for advanced nuclear in maritime and clean energy
New joint Lloyd’s Register and British Ports Association paper sets out a practical readiness pathway for ports considering nuclear-powered vessels,…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved