Energinet and 50Hertz starts tendering for Bornholm Energy Island

Danish and German TSO’s Energinet and 50Hertz have started the tendering process for key technologies of the joint project Bornholm Energy Island that will bring 3 GW of green power to German and Danish energy consumers. As a result of a market dialogue with possible vendors this summer, the partners decided to speed up the tendering in order to reserve production capacity as early as possible. Next step will be receiving bids and starting negotiations until contracts can be signed in the second half of 2024.
The market dialogue with interested vendors have shown that the Energy Island project needs start tendering early in order to reserve production capacity and keep to the project timeline. Another direct consequence of the market dialogue is that 50Hertz and Energinet will split the tender into multiple contracts in order to enable vendors interested in bidding on the HVDC stations and cables the possibility to bid on contracts within their core business, while other parts of the project will be tendered separately.
HDVC equipment for the stations in Germany and Denmark will be tendered as one joint contract which has been sent to prequalified vendors today. 50Hertz and Energinet has designed the procurement of the HVDC-breakers – a future key technology for the energy island – as an option, which can either be built as part of the initial construction – or as a separate tender at a later phase. The reason for this is that some vendors are highly interested in supplying the breakers, while others prefer to focus on their core products.
”We cannot ignore the current market situation. HVDC circuit breakers will play an important part in the operation of our Energy Island but are not crucial in the initial phase. Therefore, we have decided that it is more important to ensure a competitive bidding process and to keep up the pace of the green transition in order to secure the supply of clean electricity to consumers in Germany and Denmark.”, says Hanne Storm Edlefsen, vice president for Energy Islands at Energinet.
50Hertz has already signed a contract for the procurement of HVDC cables for Bornholm Energy Island and several other projects. Energinet has started the tender of one contract for production of cables as well as offshore installation. Onshore installation and horizontal directional drillings (HDD) will be a separate contract as well as surveying and removal of unexploded ordnance (UXO) which will also be tendered as a separate contract at a later time. Civil works and the buildings for the HDVC stations will be tendered for Denmark and Germany respectively, at a later time.
Construction on Energinets part of the project in Denmark can start once it has received an environmental permit and archaeological excavations have been completed in 2025. In Germany installation and construction can start after permits are granted by the authorities.
Related News.
October 23, 2026
Columbia Group calls for greater focus on retaining women at sea as second She Beyond Conference takes place
Columbia Group has called on the maritime industry to create a future where women can thrive, progress and lead at sea, as it celebrated the second…
October 23, 2026
Neptune Group Welcomes “NIKOS TRAVLOS”
The new vessel proudly bears the name of Neptune's founder, who laid the foundation for the creation and enduring evolution of the Group. Her…
October 23, 2026
Wildcat Defense enters into exclusive agreement to acquire Fraser Shipyards
American family firm takes the next step in its strategy to rebuild U.S. shipbuilding and repair capacity, following its offer for Austal USA.…
October 23, 2026
Kawasaki signs strategic partnership MOU with Romania’s Transgaz for Onshore Hydrogen Gas Transport
Establishing a model for large-scale hydrogen supply and transport via pipelines Kawasaki Heavy Industries, announced at the Romania–Japan…
October 23, 2026
UK P&I Club and TT Club secure regulatory approval for Thomas Miller acquisition
The UK P&I Club and TT Club announce the successful completion of their joint acquisition of the Thomas Miller Holdings group, marking a major…
October 23, 2026
Valenciaport presents its Sandbox at PEIC’26 as a tool to bridge the gap between innovation and implementation
The opening session featured a discussion between Valenciaport President Mar Chao and Valenciaport Foundation Director Antonio Torregrosa. The…
October 23, 2026
Major investments strengthen Gothenburg RoRo Terminal
Expanded terminal areas, new rail connections and modernised quays are among the investments that have strengthened Gothenburg RoRo Terminal in…
October 23, 2026
ABP appoints key roles in the Humber
Associated British Ports has made two key appointments at its container terminals strengthening its unitised operations at the ports of Immingham…
October 23, 2026
Xinhua Silk Road 2026 North Bund Forum unveils 20 shipping-related achievements
The 2026 North Bund Forum opened in Shanghai on October 20 with 20 key shipping-related achievements spanning international cooperation, green…
October 23, 2026
Ports encouraged to prepare now for advanced nuclear in maritime and clean energy
New joint Lloyd’s Register and British Ports Association paper sets out a practical readiness pathway for ports considering nuclear-powered vessels,…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved