AAL transports 12,800 FRT of vital components on single sailing for Texas LNG project

The shipment of LNG cargo included an AGR Absorber that breaks AAL’s record for the heaviest unit ever handled on its Asia-Americas Regular Trade Lane Project Heavy Lift Carrier.
AAL Shipping, this summer executed a complex operation to transport over 12,800 Freight Tonnes of heavy lift project cargo from the South Korean ports of Kunsan and Pyeongtaek to Beaumont in Texas – shipped along its in-demand regular ‘Asia to The Americas Trade Lane’ and onboard its 31,000-deadweight heavy lift vessel, the AAL Brisbane. The shipment was part of a major LNG project in the US’s second largest state, Texas.

The high value project cargo will be installed at the LNG facility’s new processing plant. It comprised multiple sized components totalling 12,800 freight tonnes, the largest of which was a 607-metric tonne AGR Absorber that measured just under 39 metres, used to remove H2S, CO2 and other organic sulphurs from raw feed gas. Some of the other large heavy lift units included a 40-metre and 436-metric tonne HP MR Absorber and three Dehydrators, weighing just shy of 200-tonnes each.

Henrik Hansen, General Manager of AAL Americas, commented, “We have a longstanding collaboration with the shippers, having successfully executed several long-haul fixtures for them in the past between Asia and the US Gulf. On this shipment, the largest unit of 607 metric tons was the heaviest piece ever lifted and carried by AAL on our trade lane between Asia and North America.”
He added, “In addition to the heavy lift cargo, this sailing also carried general and project cargoes to other US destinations and for multiple customers representing varied industry sectors. The AAL Brisbane is an A-Class second-generation premium heavy lift vessel, with a lifting capacity of 700 tonnes and cargo intake of 40,000 CBM, and she proved uniquely able to handle this complex shipment.

“From a technical perspective there were multiple challenges and loading such cargo from and discharging to barge is always a precarious process, during which exacting ballast water techniques are deployed to ensure the vessel remains perfectly upright whilst lifting and transferring the largest components. Total time required to discharge in Beaumont was 113 hours, with three and half hours needed just for the largest unit. The operation proved a great success and is down to the dedication of our engineers, ops team and the vessel’s highly experienced crew.”

With an estimated send out capacity of around 18 million tonnes of LNG per year, the facility will create hundreds of direct jobs and enhance US energy security, whilst helping to export clean energy from Texas to the world.
Related News.
October 22, 2026
Beyond Technical Skills: WISTA Cyprus explores the human side of leadership
WISTA Cyprus hosted The Art of Leadership & Emotional Mastery, an interactive workshop held on 15 October at the Alasia Hotel in Limassol,…
October 22, 2026
The human cost of sending merchant mariners into war zones extends far beyond the immediate danger of missiles and drones. It raises a harder question: who is really protecting the seafarer?
Who protects the seafarer? I have spent much of my professional life at sea. I am a Master Mariner. I have stood on the bridge, made decisions…
October 22, 2026
Loss of bridge control: Human failure is normal – context is key
When bridge control is lost in a functioning system, it can be easy to blame human error. But accidents rarely happen because of one mistake…
October 22, 2026
Danish Shipping announces the transport of live animals by sea new rules should improve safety for animals, seafarers and the environment
Revised rules on the transport of live animals by sea are being negotiated in the EU. Danish Shipping wants to ensure good animal welfare,…
October 22, 2026
Japan’s flawed shipping proposal leaves developing countries adrift
A new analysis by Opportunity Green warns governments of the wide-ranging risks posed by Japan’s proposal at the International Maritime Organization…
October 22, 2026
Intermodal Report Week 42 2026
Pls find below the Intermodal Report - Week 42 2026 Intermodal Report Week 42 2026
October 22, 2026
Allied Weekly Market Review Week 42
Pls find below the Allied - Weekly Market Review - Week 42 ALLIED - Weekly Market Report- Week 42
October 22, 2026
EU Arctic Strategy NGOs welcome EU ambition on on cutting shipping’s Arctic Black Carbon Emissions
Responding to today’s publication of the EU’s Arctic Strategy, which definitively states the EU’s intention to support International Maritime…
October 22, 2026
The final quarter of 2026 is expected to see softer bauxite flows
Chinese front-loading is expected to have run its course, pointing to softer bauxite flows in 2026 Q4. Global bauxite flows increased by 2.8% y/y…
October 22, 2026
DP World Foundation and Belewan new container terminal mark groundbreaking of AED 3.7 million school project in Indonesia
Classrooms of Hope initiative expands to Belawan, Medan with a new junior high school designed to provide modern learning facilities and greater…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved