Multiple crane operations demand heightened flexibility for AAL

This Spring has seen AAL Shipping undertake the long-haul transport of some impressive heavy lift cranes and related components for port and terminal development projects worldwide. These have included an operation to move four 439-tonne Liebherr shore cranes from Shuaiba in Kuwait to Haiphong in Vietnam for a new dry dock facility. A second operation comprised two shipments of six new-build Kalmar Automated Stacking Cranes from Taicang and Shanghai to Melbourne, Australia, for a container terminal expansion programme.

Four Second-Hand Heavy Lift Liebherr Cranes Demand Last Minute Recalibration
Project heavy lift cargo operations are complex at the best of times and made more challenging when the cargo involved is older and its integrity and even specification are in question.

Yahaya Sanusi, Deputy Head of Transport Engineering at AAL, explained, “This operation involved the transport onboard the 31,000dwt heavy lift mega-size ‘AAL Melbourne’ of four second-hand Liebherr crane units. The lead time of this project was extremely short, as the client had been left stranded by another carrier, realising the operational parameters were beyond their scope. Three of the units were the LMH 500 series and the other an LMH 550. These are some of the biggest cranes in the series, each weighing more than 400 tonnes, 35 metres tall and featuring a jib length of close to 55 metres.

“The loading of cranes of different size and of an older age required detailed preparation, made more complicated by the fact that the delivered units were in far poorer condition than expected and documentation provided was inaccurate. This not only required on-site stowage plan adjustment by our attending CSI, but also the re-calibration of each jib’s centre of gravity to ensure lifting stability could be guaranteed. Furthermore, we had to drive the first three units around deck to optimise space before the fourth unit could be loaded, which involved building bridges to connect four-metre gaps between hatch covers with heavy load platforms and corresponding ramps. Due to the poor condition of the units, we dealt with burst crane tyres, crane engine malfunction and resulting delays – handled by our crew and attending team with grit and determination.”

He concluded, “The cranes were extremely tall and affected bridge visibility, requiring special permission from the Flag State administration and further safety precautions, including the engagement of an additional safety officer on the bridge. At the port of Haiphong, the four units had to be discharged to a barge that was not self-trimming, which meant we could only discharge one crane at a time and to specific areas of the vessel. With so many ships passing closely by and generating wake, discharging to barge in Haiphong requires perfect timing. Despite all challenges, we delivered the cargo safely and within laycan.”

Six Giant Kalmar Automated Stacking Cranes (ASC) Pose Visibility & Size Challenges
AAL also recently shipped three ASCs, each 35 metres wide and 215 tonnes, from Taicang in China to Melbourne, onboard the 31,000dwt heavy lift mega-size ‘AAL Hong Kong’. A second sailing is planned with sister vessel ‘AAL Shanghai’ in early July to transport three further cranes of the same type into the Victoria State Capital from Shanghai. All six cranes are being shipped for cargo handling solutions provider Cargotec for use in Melbourne’s Victoria International Container Terminal (VICT), as part of an ongoing expansion programme for which AAL already shipped 20 ASC units in 2016.

The massive 3,000 sqm clear weather deck space of the A-Class proved ideal for these 35-metre-long, 13-metre-wide, and 27-metre-high units, enabling the safe stowage of two of the cranes side-by-side. Having already successfully shipped 20 of these units on five sailings from China to Australia in the past for Cargotec, AAL provided the experience and technical know-how that the customer demanded.

Nicola Pacifico, Head of Transport Engineering at AAL, commented, “Visibility challenges posed by these tall units required early dialogue with local authorities and other stakeholders to establish and then secure necessary safety requirements for operational approval. Multiple diagrams, extensive documentation, detailed safety analyses and a raft of preventive measures were prepared and delivered through a strong collaborative effort involving AAL’s Engineering and Operations teams, and our Technical and Crew Manager, Columbia Shipmanagement (CSM).
“Measures undertaken included the deployment of CCTV cameras to compensate for blind spots, establishing forward radar, and employing additional watchkeeping, tugs and pilot assistance during departure and arrival at port. Bespoke adaptations to accommodate the significant size of the cranes included the use of bolsters to extend deck width on the starboard side, removing the support of ship crane number three to enable a suitable swing angle during loading and discharge, and the additional stowing of the crane’s jib in an upper position during sea voyage.”
Related News.
October 22, 2026
Beyond Technical Skills: WISTA Cyprus explores the human side of leadership
WISTA Cyprus hosted The Art of Leadership & Emotional Mastery, an interactive workshop held on 15 October at the Alasia Hotel in Limassol,…
October 22, 2026
The human cost of sending merchant mariners into war zones extends far beyond the immediate danger of missiles and drones. It raises a harder question: who is really protecting the seafarer?
Who protects the seafarer? I have spent much of my professional life at sea. I am a Master Mariner. I have stood on the bridge, made decisions…
October 22, 2026
Loss of bridge control: Human failure is normal – context is key
When bridge control is lost in a functioning system, it can be easy to blame human error. But accidents rarely happen because of one mistake…
October 22, 2026
Danish Shipping announces the transport of live animals by sea new rules should improve safety for animals, seafarers and the environment
Revised rules on the transport of live animals by sea are being negotiated in the EU. Danish Shipping wants to ensure good animal welfare,…
October 22, 2026
Japan’s flawed shipping proposal leaves developing countries adrift
A new analysis by Opportunity Green warns governments of the wide-ranging risks posed by Japan’s proposal at the International Maritime Organization…
October 22, 2026
Intermodal Report Week 42 2026
Pls find below the Intermodal Report - Week 42 2026 Intermodal Report Week 42 2026
October 22, 2026
Allied Weekly Market Review Week 42
Pls find below the Allied - Weekly Market Review - Week 42 ALLIED - Weekly Market Report- Week 42
October 22, 2026
EU Arctic Strategy NGOs welcome EU ambition on on cutting shipping’s Arctic Black Carbon Emissions
Responding to today’s publication of the EU’s Arctic Strategy, which definitively states the EU’s intention to support International Maritime…
October 22, 2026
The final quarter of 2026 is expected to see softer bauxite flows
Chinese front-loading is expected to have run its course, pointing to softer bauxite flows in 2026 Q4. Global bauxite flows increased by 2.8% y/y…
October 22, 2026
DP World Foundation and Belewan new container terminal mark groundbreaking of AED 3.7 million school project in Indonesia
Classrooms of Hope initiative expands to Belawan, Medan with a new junior high school designed to provide modern learning facilities and greater…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved























