Final monopile installed at Hollandse Kust Noord offshore wind farm by Van Oord

The final monopile for CrossWind’s Hollandse Kust Noord wind farm was successfully installed by Van Oord this week, bringing the total to 70. The offshore wind farm is located 18.5 kilometres off the coast of the Netherlands, near the seaside resort of Egmond aan Zee. Once finished it will have a total installed capacity of 759 MW, generating at least 3.3 TWh per year. This is enough renewable electricity to meet 2.8% of the Netherlands’ electricity demand. The monopiles are the foundations for the wind turbines. The first monopile was installed less than four months ago, on October 17th 2022.
Roeland Ris, Project Director Van Oord: ‘After an extensive period of preparations, it’s great to now actually see the outlines of the offshore wind farm. Thanks to the project team and all partners involved who worked with great efforts and enthusiasm on reaching this important milestone to have all monopiles in place. With the supply of secondary steel and inter array cables on target and our offshore installation vessels fully operational, the construction of the Hollandse Kust Noord offshore wind farm is progressing well on schedule.’
Wybren de Vries, Balance of Plant Package Manager at CrossWind said: ‘The installation of the monopiles was an immense operation, with the monopiles weighing between 788 tons and 960 tons each. During the installation works CrossWind and Van Oord promoted and maintained an open culture, in which we acted as one team. I am convinced that this approach defined a big part of our success in reaching this milestone in a safe and timely manner.’
Van Oord installed all 70 monopiles in a short period of time despite strong wind and cold weather. As a Balance of Plant contractor of CrossWind, Van Oord activities encompass the design, engineering, procurement, construction and installation of the wind turbine foundations. Van Oord engaged DEME to deploy the jack-up vessel Innovation to install the monopiles.
Van Oord is also involved in the design, engineering, procurement and installation of the inter array cables, as well as the transport and installation of the wind turbines themselves. Meanwhile Van Oord’s offshore installation vessel MPI Resolution is installing secondary steel to complete the foundations. The secondary steel sets consist of boat landings, main access platforms (with davit cranes) and internal platforms. The platforms will be used for maintenance activities once the wind farm is operational. Van Oord will deploy cable-laying vessel Nexus to install the cables starting in March this year.
Related News.
September 3, 2026
Cyprus Maritime Innovation takes Centre Stage at SMM Hamburg 2026
Underscoring its expanding role as a premier international hub for cutting-edge maritime technology and sustainable shipping, the Republic of Cyprus…
September 3, 2026
Trump seeks to refill US oil reserve with Venezuela deal but faces long delay
U.S. President Donald Trump said on the 30th (local time) that he would refill the U.S. Strategic Petroleum Reserve, which has been depleted with…
September 3, 2026
US Navy Official visits South Korean Shipyards in private
With U.S. President Donald Trump pushing a plan to allow overseas construction of U.S. warships, attention is focusing on whether the building of…
September 3, 2026
SES and De Boer Marine expand collaboration with FlexMaritime deployment across Global Markets
SES, a leading space solutions company, and De Boer Marine, a leading provider of top-quality marine equipment and maritime connectivity services,…
September 3, 2026
New ESG guidance to help maritime industry turn sustainability into commercial advantage
New framework helps shipowners and ports align ESG strategy with access to capital, charterer expectations and long-term asset value. Maritime…
September 3, 2026
Britannia P&I Club analysis finds four in five crew deaths linked to illness rather than accidents
New report highlights cardiovascular disease as leading cause of fatalities and raises concerns over mental health risks among younger seafarers.…
September 3, 2026
The Swedish Club launches new Loss Prevention podcast, Knot Another Lesson
The Swedish Club has launched Knot Another Lesson, a new podcast exploring the practical lessons, emerging risks and operational challenges shaping…
September 3, 2026
Lloyd’s Register appoints Jens Grunenberg as Senior Representative for Germany
Lloyd’s Register has appointed Jens Grunenberg as its Senior Representative for Germany, effective 1 September. Based in Hamburg, Grunenberg will…
September 3, 2026
Indian Register of Shipping sets sights on Hamburg for European Expansion
Indian Register of Shipping, a leading international classification society and full member of the International Association of Classification…
September 3, 2026
MOL completes Merger of 6 Ship Management Companies
Unifying Management of Over 200 Vessels and Strengthening Safety Mitsui O.S.K. Lines, announced that it has completed the integration of the MOL…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved