Engineering and environmental permitting for TIWI H2 export project advances

GEV acknowledges that its proposed Tiwi H2 Export Project is located on the traditional lands of the Munupi people. It is a privilege to have the support and such a close working relationship with the Munupi Landowners, Tiwi Land Council, Tiwi Plantation Corporation, NT Government, Office of Township Leasing and NT Port and Marine.
HIGHLIGHTS
- Several permissions granted for the 2.8 GW green hydrogen export project on the Tiwi Islands, allowing the EPA Referral submission to be completed. The project will deliver a fully integrated green hydrogen production and export supply chain, producing up to 100,000 tonnes per annum of green hydrogen for export into the Asia-Pacific region.
- Strong support from the Munupi Landowners and Tiwi Plantation Corporation Board continues with permission granted for an increase in land area for environmental and engineering studies to be undertaken on Tiwi land for solar transmission, and hydrogen production and port facilities.
- Required engineering studies are advancing, covering the key areas of solar generation, power transmission and water desalination that support the Referral submission.
- Environmental consultants are underway with on-ground field surveys to prepare the environmental Referral Submission in the first half of 2022.
- Experienced consultants engaged to design the proposed 2.8 GW solar farm and transmission line, covering construction, operation, and generation modelling.
- GEV’s 2022 Tiwi H2 development program remains fully funded.
Global Energy Ventures Ltd (ASX: GEV, the Company) is pleased to provide the following update on its 2.8 GWgreen hydrogen export project on the Tiwi Islands, Northern Territory, Australia (Tiwi H2). ADVANCING A LOW ENVIRONMENTAL FOOTPRINTGEV continues to pursue a low environmental footprint for Tiwi H2 that also supports the target for an investment decision in 2023 and first exports in 2026. Refer to Figure 2 for an illustration of the following elements:
- > 2.8 GW solar site: planned to be built on existing plantation land and now expanded to ~2,580 hectares.
- > Transmission line: planned to be built on a 50-metre corridor of native flora (~120 ha) following the existing road 30km from the proposed solar farm to Port Melville. The selection of the actual route and footingplacement will be determined to minimise its environmental impact.
- > Hydrogen facilities & Existing port infrastructure: planned to be built on 32 hectares of existing clearedindustrial precinct land at Port Melville and an additional 40 hectares of native flora.
The Company is now advancing a Referral submission to provide sufficient information to the NT Environment Protection Authority (NT EPA) so that a decision can be made on the level of assessment required for the Tiwi H2 Project. GEV expects to lodge its Referral submission in the June quarter of 2022, with the NT EPA decision to follow in the September quarter 2022.
MUNUPI LANDOWNER SUPPORT CONTINUES WITH AN INCREASE IN LAND AVAILABLE
GEV continues to receive support from the various stakeholders involved in the Tiwi H2 project to be located on Munupi land, Melville Island. At a recent meeting convened with Munupi Landowners and the Tiwi Plantation Corporation, several permissions were requested and granted, allowing the EPA Referral submission to be completed, including consultants to be on-country for required environmental surveys, with further engineering surveys and studies to follow in the first half of 2022 and included in the project pre-feasibility.
GEV is pleased to announce that one of the key permissions granted includes an increase in the land available to the Referral submission, with the scope to include solar generation now based on ~2,580 hectares (up from 1,800 hectares ~120 hectares of land for a transmission line and an additional 40 hectares (for a total of 72 hectares) of land adjacent to the existing port facilities is for hydrogen production and compression.
Munupi Landowners also granted permissions to GEV for the solar monitoring to get underway in the September quarter of 2022 and will be based on agreed sites for clearing and installation. Further meetings and permissions will be required at various stages for the project as and when future activities on Munupi land are required.
GEV’s Executive Director and Chief Development Officer, Garry Triglavcanin, commented: “Tiwi H2 continues to receive the support from the Munupi Landowners, as demonstrated with all permissions requested being granted at a recent meeting held on Melville Island. Permissions include an increase in available land to be made available for the project, consultants to be on-country for required environmental surveys, and further engineering surveys and studies to follow in the June quarter of 2022.
“The project’s Referral submission to the EPA is advancing and on track for completion in the June quarter. This is an important step forward, as the environmental process is likely to drive the project schedule for a target investment decision in the latter part of 2023.
“GEV is also advancing the design of the 2.8 GW solar site and transmission line with the appointment of consultants with significant design, construction, and operational experience in locations across northern Australia.
ENGAGEMENT OF SOLAR GENERATION AND TRANSMISSION DELIVERY EXPERTISE
To advance the design of the solar farm and transmission line, GEV has engaged CE Partners, a specialist consulting group in solar developments who will provide GEV with project delivery expertise on the proposed 2.8 GW solar farm and transmission line, covering construction, operation, and generation modelling. CE Partners will bring +20 years of delivery expertise on renewable energy projects across Australia, including the Cohuna Solar Farm, Gannawarra Solar Farm, Gannawarra Energy Storage System, Wemen Solar Farm and Clermont Solar Farm
NEXT STEPS FOR THE PROJECT
Figure 2: Tiwi H2 Project with additional land for environmental survey
Source: GEV
- Environmental and engineering surveys and studies will continue to be undertaken, mostly on-country, in line with the permissions granted to the Company and as required to complete the Referral submission.
- Prepare for and commence solar monitoring in two locations in the September quarter of 2022 for a period of 12 months. Permissions have been granted, with associated monitoring agreements with the Tiwi Plantation Corp to be concluded in the June quarter of 2022.
- Request for proposal and appointments of lead consultants in the June quarter of 2022 to commence detailed engineering and support the target of financial close of an initial phase of development by the second half of 2023.
4. GEV to continue its preliminary marketing activities of green hydrogen from Tiwi H2 with several strategies underway to identify bankable parties for potential offtake and investment in the markets of Singapore, Japan, Korea and Indonesia. One activity includes GEV’s selection for participation in Austrade’s Team Australia Stand at the World Hydrogen Summit, Rotterdam, in May.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved