Ocean Harvesting commissions test-rig for InfinityWEC power take-off with instant force control capabilities

Ocean Harvesting Technologies has commissioned a Hardware in the Loop (HIL) test rig at scale 1:10 to validate the InfinityWEC power take-off (PTO) with instant force control capabilities.
The test rig simulates the buoy motion with force feedback from the PTO system, and will be used to validate the complete functionality of the PTO and control system as in a complete WEC for real sea conditions. The functionality includes (i) instant force control capability in combination with efficiency and constraint-aware predictive control, amplifying energy capture, and (ii) a soft two-stage end stop, holding the buoy submerged through the crest of large waves to ensure both survival and continued, reliable power production even in the harshest conditions. The test rig will later be used as a platform to develop and evaluate AI-based control strategies and design principles, to further refine InfinityWEC’s capability to capture maximum power from each wave. The project is co-financed by the Swedish Energy Agency and will be completed by February 2022.
The developed control system will be used in the sea trial of a complete InfinityWEC system at scale 1:3, to take place on the Swedish west coast. The sea trial project is planned to start in 2022 and key suppliers are Sigma Energy & Marine, Acumo/NSK, and Beckhoff, among others. RISE Research Institutes of Sweden is partnering in the project and will be responsible for validation of the integrity of the hull that includes sustainable high performance concrete and biofouling as outcomes in the research project WEChull, financed by the Swedish Energy Agency.
The sea trial in scale 1:3 will demonstrate that InfinityWEC is on track towards LCoE 100 EUR / MWh at 100 MW installed capacity and < 35 EUR / MWh at 5 GW installed capacity. System performance will be tested in real sea conditions and results will be used to validate and calibrate the simulation tools to predict energy yield, ownership cost, affordability, availability and process efficiency. The commercial-scale single device demonstration is planned to start in 2024, to be followed by array installations on commercial terms. The road map to commercialization follows the staged development process recommended in the Ocean Energy Systems (OES) framework, a technology collaboration program by the International Energy Agency (IEA).
OHT is, furthermore, performing a feasibility study on how a wave farm installation could provide electricity to one of Lundin Energy Norway’s oil & gas platforms. The study includes sizing and specification of the wave farm, energy storage, handling procedures and a life cycle cost assessment. OHT also participates in three joint industry collaborative projects led by RISE: WECHull (hull materials), Seasnake (dynamic power cables) and NextWave2 (sensor technology and algorithms for wave prediction).
OHTs technology is protected by five patent families filed since 2017, covering all vital aspects of the power take-off and control system, the buoy design and general arrangements.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved