Sakhalin-2 Project resumes Liquefied Natural Gas production

The Amur River LNG carrier has departed from the Port of Prigorodnoye with the first LNG cargo loaded after the Sakhalin-2 integrated gas system major turnaround campaign. LNG train 1 has been restarted, while post-shutdown commissioning continues at train 2
The turnaround campaign took place at several assets, including the Lunskoye-A offshore gas production platform, the onshore processing facility, OPF compression construction site, booster station No. 2, and the Prigorodnoye production complex.
“Some activities were completed for the first time, not only in Sakhalin-2 project’s history, but also in Russia. Once of such unique technical challenges was the replacement of two out of the four LNG loading arms at the LNG jetty. This complex operation was carried out using Pijlgracht, a specialised vessel equipped with two main cranes with a lifting capacity up to 700 metric tonnes each,” said Alexander Singurov, Deputy Production Director and Prigorodnoye Asset Manager.
“At the production complex, we also modified the mixed refrigerant compressor and the emergency shutdown system,” added Mr Singurov.
According to Evgeny Udovenko, Head of Engineering and Maintenance, the 2021 major turnaround campaign was preceded by a lot of preparations and case reviews that took into account COVID-19-related risks and international vendors’ personnel travel restrictions.
Overall, 3,000 company and contractor team members completed approximately 1,600 work orders and accumulated over 1.2 million man-hours without a single lost time incident.
“Moreover, in view of the scale and duration of our summer turnaround campaign, the company decided to complete some of the scope originally scheduled for autumn and winter 2021 and for 2022 during this TA”, said Evgeny Udovenko.
He also mentioned that, thanks to the scheduled and extra maintenance performed this year based on equipment inspections and diagnostics, the company intends to skip a major turnaround next year. This will allow Sakhalin Energy to reduce OPEX, do activity planning more efficiently and effectively, and transition the entire integrated gas chain to a four-year maintenance cycle going forward. With this approach, each train will be shut down once every two years.
Related News.
September 3, 2026
Cyprus Maritime Innovation takes Centre Stage at SMM Hamburg 2026
Underscoring its expanding role as a premier international hub for cutting-edge maritime technology and sustainable shipping, the Republic of Cyprus…
September 3, 2026
Trump seeks to refill US oil reserve with Venezuela deal but faces long delay
U.S. President Donald Trump said on the 30th (local time) that he would refill the U.S. Strategic Petroleum Reserve, which has been depleted with…
September 3, 2026
US Navy Official visits South Korean Shipyards in private
With U.S. President Donald Trump pushing a plan to allow overseas construction of U.S. warships, attention is focusing on whether the building of…
September 3, 2026
SES and De Boer Marine expand collaboration with FlexMaritime deployment across Global Markets
SES, a leading space solutions company, and De Boer Marine, a leading provider of top-quality marine equipment and maritime connectivity services,…
September 3, 2026
New ESG guidance to help maritime industry turn sustainability into commercial advantage
New framework helps shipowners and ports align ESG strategy with access to capital, charterer expectations and long-term asset value. Maritime…
September 3, 2026
Britannia P&I Club analysis finds four in five crew deaths linked to illness rather than accidents
New report highlights cardiovascular disease as leading cause of fatalities and raises concerns over mental health risks among younger seafarers.…
September 3, 2026
The Swedish Club launches new Loss Prevention podcast, Knot Another Lesson
The Swedish Club has launched Knot Another Lesson, a new podcast exploring the practical lessons, emerging risks and operational challenges shaping…
September 3, 2026
Lloyd’s Register appoints Jens Grunenberg as Senior Representative for Germany
Lloyd’s Register has appointed Jens Grunenberg as its Senior Representative for Germany, effective 1 September. Based in Hamburg, Grunenberg will…
September 3, 2026
Indian Register of Shipping sets sights on Hamburg for European Expansion
Indian Register of Shipping, a leading international classification society and full member of the International Association of Classification…
September 3, 2026
MOL completes Merger of 6 Ship Management Companies
Unifying Management of Over 200 Vessels and Strengthening Safety Mitsui O.S.K. Lines, announced that it has completed the integration of the MOL…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved