Sakhalin-2 Project resumes Liquefied Natural Gas production

The Amur River LNG carrier has departed from the Port of Prigorodnoye with the first LNG cargo loaded after the Sakhalin-2 integrated gas system major turnaround campaign. LNG train 1 has been restarted, while post-shutdown commissioning continues at train 2
The turnaround campaign took place at several assets, including the Lunskoye-A offshore gas production platform, the onshore processing facility, OPF compression construction site, booster station No. 2, and the Prigorodnoye production complex.
“Some activities were completed for the first time, not only in Sakhalin-2 project’s history, but also in Russia. Once of such unique technical challenges was the replacement of two out of the four LNG loading arms at the LNG jetty. This complex operation was carried out using Pijlgracht, a specialised vessel equipped with two main cranes with a lifting capacity up to 700 metric tonnes each,” said Alexander Singurov, Deputy Production Director and Prigorodnoye Asset Manager.
“At the production complex, we also modified the mixed refrigerant compressor and the emergency shutdown system,” added Mr Singurov.
According to Evgeny Udovenko, Head of Engineering and Maintenance, the 2021 major turnaround campaign was preceded by a lot of preparations and case reviews that took into account COVID-19-related risks and international vendors’ personnel travel restrictions.
Overall, 3,000 company and contractor team members completed approximately 1,600 work orders and accumulated over 1.2 million man-hours without a single lost time incident.
“Moreover, in view of the scale and duration of our summer turnaround campaign, the company decided to complete some of the scope originally scheduled for autumn and winter 2021 and for 2022 during this TA”, said Evgeny Udovenko.
He also mentioned that, thanks to the scheduled and extra maintenance performed this year based on equipment inspections and diagnostics, the company intends to skip a major turnaround next year. This will allow Sakhalin Energy to reduce OPEX, do activity planning more efficiently and effectively, and transition the entire integrated gas chain to a four-year maintenance cycle going forward. With this approach, each train will be shut down once every two years.
Related News.
November 9, 2026
Global study finds Cyprus ranks SEVENTH and set for $1.1 billion AI GDP boost
Cyprus beats India and New Zealand to come SEVENTH in major AI study – with potential €1.1 billion GDP boost and youth jobs opportunity Some 86% of…
November 9, 2026
Global shipping’s trillion dollar climate bill according to Zero Carbon Analytics
A new study by Zero Carbon Analytics finds that emissions from international shipping cost the global economy around USD 963 billion between 1990…
November 9, 2026
Keeping Children Safe Online at Sea Seafy® earns friendly WiFi Certification across 26 vessels
Seafy becomes Friendly WiFi’s first partner in the maritime sector, helping protect kids from harmful content online. Friendly WiFi is delighted…
November 9, 2026
MarinePALS keeps seafarers’ mental wellbeing results private from employers
MarinePALS has launched ‘MyMood’, a mental wellbeing self-check that enables seafarers to consider whether they need support without their individual…
November 9, 2026
ShipManager joins Star Information Systems to accelerate the maritime industry’s transition to cloud
CFARER, a DNV Company selects Star Information Systems as the longterm home for ShipManager and its cloud future Star Information Systems (Star)…
November 9, 2026
Seafarer experience must shape maritime technology, initial STEER Project report finds
New research finds technology can shift rather than remove risk as The Nautical Institute, with support from Lloyd’s Register Foundation, calls for…
November 9, 2026
New LR service targets cargo disruption when trade routes fail
New LR Advisory service helps ports, governments and logistics operators respond to disruption, protect critical cargo flows and strengthen trade…
November 9, 2026
DORIC WEEKLY INSIGHT 06 NOVEMBER 2026
Please find below the DORIC Market Insight for the week ending 06th November 2026. Weekly Report 06.11.2026
November 9, 2026
BIMCO Shipping Number of the Week
Coal shipments to India drop 7%, but limited recovery may lie ahead "Between January and October, coal shipments to India dropped 7% y/y due to the…
November 9, 2026
Hapag-Lloyd marks 20 years in South Africa and targets further growth
South Africa has become a cornerstone of Hapag-Lloyd's business in Africa Hapag-Lloyd surpasses 1 million TEU in Africa for the first time in its…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved