Jan De Nul completes installation of all wind turbines at TPC Offshore Wind Farm

The project was kicked off in September 2018 with the preparatory onshore cable works. On 12 June 2021, Jan De Nul’s Offshore Jack-Up Installation Vessel Taillevent successfully completed the installation of the last 5.2 MW Hitachi wind turbine for Taiwan Power Company (TPC).
Jan Kop, Project Director TPC Project for Jan De Nul Group: “With this major milestone we have now reached the final stretch of the project which has challenged us in many ways, not even imaginable when we started more than three years ago. The COVID-19 restrictions and regulations implemented by authorities in Taiwan and around the globe have affected the project, but we have always continued with great commitment finalizing the installation of the cables, jacket foundations and wind turbines. We thank our on- and offshore teams for the great teamwork.”
Wind turbines with a downwind rotor
The TPC Offshore Wind Farm near Fangyuan, 8 kilometres off the West coast of Taiwan, is constructed in a region where typhoons are very common.
Each 5.2 MW wind turbine is installed on a jacket foundation with transition piece, anchored to the seabed using four steel pin piles, and equipped with wind turbines with a downwind rotor.
Consortium partner Hitachi Ltd. pioneered this design by obtaining the Wind Turbine Class T certification, an international standard on wind-resistant design recognising the need in regions subject to frequent typhoons.
Construction of Taiwan’s first state-owned offshore wind farm
Jan De Nul kicked off the construction works in September 2018 with the preparatory onshore cable duct installation works to connect the existing onshore substation to the cable interface near shore.
Fabrication of the different foundation components was initiated in 2019. The first foundations left the South Korean fabrication yards in April 2020 to the offshore wind farm site in Taiwan.
In June 2020, Jan De Nul installed the first pin piles and connected the first export cable to shore. By early August of that same year, the very first jacket foundation was installed and anchored to the seabed. And on 15 September the first wind turbine was erected.
Consortium Jan De Nul-Hitachi
The ‘Offshore Windfarm Phase 1 Project – Demonstration’ was awarded to the Consortium Jan De Nul – Hitachi in February 2018.
Jan De Nul Group is responsible for the design, fabrication and installation of the foundations, the provision of the offshore vessel for the installation of the wind turbines, the supply and installation of the cables off- and onshore as well as upgrading an electrical substation. Hitachi Ltd. is in charge of manufacturing, assembly, installation and other works related to the offshore wind turbines with downwind rotor.
Subsequently, the Consortium is responsible for the operation and maintenance (O&M) of the offshore wind farm over five years.
The project has challenged us in many ways, but we have always continued with great commitment finalizing the installation. We thank our on- and offshore teams for the great teamwork.
Jan Kop
Project Director TPC Offshore Wind Farm at Jan De Nul Group
Related News.
November 9, 2026
Global study finds Cyprus ranks SEVENTH and set for $1.1 billion AI GDP boost
Cyprus beats India and New Zealand to come SEVENTH in major AI study – with potential €1.1 billion GDP boost and youth jobs opportunity Some 86% of…
November 9, 2026
Global shipping’s trillion dollar climate bill according to Zero Carbon Analytics
A new study by Zero Carbon Analytics finds that emissions from international shipping cost the global economy around USD 963 billion between 1990…
November 9, 2026
Keeping Children Safe Online at Sea Seafy® earns friendly WiFi Certification across 26 vessels
Seafy becomes Friendly WiFi’s first partner in the maritime sector, helping protect kids from harmful content online. Friendly WiFi is delighted…
November 9, 2026
MarinePALS keeps seafarers’ mental wellbeing results private from employers
MarinePALS has launched ‘MyMood’, a mental wellbeing self-check that enables seafarers to consider whether they need support without their individual…
November 9, 2026
ShipManager joins Star Information Systems to accelerate the maritime industry’s transition to cloud
CFARER, a DNV Company selects Star Information Systems as the longterm home for ShipManager and its cloud future Star Information Systems (Star)…
November 9, 2026
Seafarer experience must shape maritime technology, initial STEER Project report finds
New research finds technology can shift rather than remove risk as The Nautical Institute, with support from Lloyd’s Register Foundation, calls for…
November 9, 2026
New LR service targets cargo disruption when trade routes fail
New LR Advisory service helps ports, governments and logistics operators respond to disruption, protect critical cargo flows and strengthen trade…
November 9, 2026
DORIC WEEKLY INSIGHT 06 NOVEMBER 2026
Please find below the DORIC Market Insight for the week ending 06th November 2026. Weekly Report 06.11.2026
November 9, 2026
BIMCO Shipping Number of the Week
Coal shipments to India drop 7%, but limited recovery may lie ahead "Between January and October, coal shipments to India dropped 7% y/y due to the…
November 9, 2026
Hapag-Lloyd marks 20 years in South Africa and targets further growth
South Africa has become a cornerstone of Hapag-Lloyd's business in Africa Hapag-Lloyd surpasses 1 million TEU in Africa for the first time in its…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved