Equinor announced revised start-up date for Hammerfest LNG

Based on extensive analyses and mapping of damages, Equinor has updated the schedule for repair and start-up of the LNG plant on Melkøya after the fire on 28 September 2020. Due to the comprehensive scope of work and Covid-19 restrictions, the revised estimated start-up date is set to 31 March 2022.
Even though the fire in September 2020 was limited to the air intake of one of the plant’s five big gas turbines, the fire and firefighting caused substantial damage to the plant.
“We have worked systematically on getting an overview of the damages and scope of work to bring the plant’s technical condition back to the required standard. There is still some uncertainty related to the scope of work, however our best start-up estimate is 31 March 2022, based on current knowledge. Safety is our top priority, and we will not start the plant before it can be done safely,” says Grete B. Haaland, Equinor’s senior vice president for onshore plants.
Operational measures to handle the Covid-19 situation have affected the follow-up progress after the fire. The project for planning and carrying out repairs of the Hammerfest LNG plant must always comply with applicable guidelines for handling the infection situation in society. The project has already introduced several measures that allow us to have fewer workers on site at the same time than previously expected. There is still uncertainty related to how the Covid-19 development will impact the project progress.
More than 70,000 unique equipment components were potentially exposed to seawater during the firefighting. The components have been systematically checked after the fire, and a repair plan for securing the plant’s integrity has been prepared.
The most time-consuming activity appears to be the replacement of electric cables connected to the power station where the fire occurred. Inspections show that more than 180 km of cable must be replaced. New cables have been ordered and will arrive Melkøya during this spring/summer.
Other equipment components are being procured for delivery in the summer/autumn of 2021. Several major equipment components, including several compressors, must also be taken out of the plant, and sent to the supplier for repair.
“Employees and suppliers have done a demanding and important job of getting an overview of the damages and making plans for returning the plant safely to operation. We are also very grateful for the support we have received, and is still receiving, from the local community of Hammerfest. The Hammerfest LNG plant has been, and will continue to be, a strong contributor to value creation for the local community and owners,” says Haaland.
Equinor’s internal investigation of the fire is still being conducted. The company will revert to findings and conclusions when the investigation is completed.
Related News.
November 10, 2026
RINA’s Hellenic Technical Committee puts energy-efficient newbuilding design and AI in focus
Project Mermaid, battery integration and practical AI applications highlight opportunities for more efficient ship design and fleet operations…
November 10, 2026
From mine to market – NORDEN connects Comilog’s manganese ore with global markets
NORDEN’s dedicated transhipment operation in Gabon, run under a long term contract with long-standing customer Comilog, has loaded more than 54…
November 10, 2026
Oldendorff reflags two capesize vessels to Germany
Oldendorff Carriers is reflagging two of its Capesize bulk carriers to Germany, underlining the company’s long standing ties to the country and its…
November 10, 2026
AskChief surpasses 100-vessel milestone in under a year and opens its specialised maritime AI to the wider market
Putting each company’s own knowledge to work for maritime Technical and HSQE teams. AskChief, Specialised AI for maritime Technical and HSQE…
November 10, 2026
Dalian Maritime University’s Yu Jiajia receive 2027 IMO Gender Equality Award
From the bridge to the classroom, Ms Yu has helped build a more inclusive maritime sector in China, serving as a role model for the global maritime…
November 10, 2026
“K” LINE releases video update on forecasts for FY2026 and progress of the medium-term management plan
Kawasaki Kisen Kaisha, has released a video on its official website explaining its forecasts for FY2026 and progress of its Medium-Term Management…
November 10, 2026
MOL and MOL CAREER sign 3-way deal with Nagasaki Prefecture to promote recruitment and retention of foreign workers
Mitsui O.S.K. Lines, and MOL CAREER, have entered into a tripartite partnership agreement with Nagasaki Prefecture to promote the revitalization of…
November 10, 2026
Hapag-Lloyd completes acquisition of 25% stake in APM Terminals Maasvlakte II
Transaction successfully completed following antitrust approval Investment strengthens Hapag-Lloyd’s terminal portfolio and position in Rotterdam…
November 10, 2026
11th chainPORT annual meeting at Tanger Med Focuses on scaling AI in ports
Representatives from leading ports around the world gathered in Tangier, Morocco, on 29 and 30 October for the 11th chainPORT Annual Meeting, hosted…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved





















…