Jan De Nul halfway through installation of 600MW kriegers flak wind farm

On 27 January, Jan De Nul, Siemens Gamesa and Vattenfall successfully installed the very first wind turbine for the Kriegers Flak offshore wind farm. The last turbine is scheduled to be installed in mid-June, approximately 4.5 months after the start of this installation campaign.
This offshore wind farm will become the largest in Denmark and will increase Denmark’s offshore wind production by no less than 16 percent.
Bert Reynvoet, Project Manager of Jan De Nul Group for the Kriegers Flak offshore wind farm: “We are proud that we can tick off this milestone nicely on schedule. All 72 wind turbines must be installed within a period of 4.5 months. Our customer’s wishes are paramount and despite the challenging winter weather conditions in the Baltic Sea, COVID-19 and challenging soil conditions for our jack-up installation vessel, we have managed until today to strictly adhere to the installation schedule. Thanks to the commitment, flexibility and professionalism of our co-workers!”
Roenne as marshalling harbour
For the first time since its expansion in 2018, the port of Roenne on the Danish island of Bornholm is serving as marshalling harbour for the construction of an offshore wind farm.
The components of the Siemens Gamesa wind turbines are delivered from Denmark’s mainland. In Roenne, the various parts are assembled. In sets of four wind turbines, they are loaded on board Jan De Nul’s jack-up installation vessel Vole au vent, after which the vessel sails to the offshore installation site off the Danish east coast.
Bert Reynvoet: “When a large installation vessel like the Vole au vent enters a port for the first time, it is always a bit exciting. Moreover, it was new for everyone involved, but thanks to the top service of the port and our local partners, Roenne turns out to be a perfect marshalling harbour. An absolute boost in these challenging times.”
Long-term cooperation
In 2017 and 2018, Jan De Nul Group already designed, built and installed two large Gravity Based Foundations for the offshore high-voltage substations of this new offshore wind farm.
Jan De Nul built both concrete structures of 8,000 and 10,000 tonnes on a floating pontoon in the port of Ostend (Belgium) and then tugged them to Denmark. In the Baltic Sea, the crane vessel Rambiz installed both foundations on the seabed with the utmost precision.
About the Kriegers Flak offshore wind farm
- 600 MW will be the total production capacity, which equals the annual electricity needs of about 600,000 Danish households.
- 72 wind turbines of 187 metres high will cover an offshore area of 132 km² at 15 to 40 kilometres off the Danish East coast.
- About 170 kilometres of subsea cables will be installed to connect the offshore wind farm to the Danish grid.
- The wind farm is expected to be fully operational by the end of 2021.
Related News.
September 3, 2026
Cyprus Maritime Innovation takes Centre Stage at SMM Hamburg 2026
Underscoring its expanding role as a premier international hub for cutting-edge maritime technology and sustainable shipping, the Republic of Cyprus…
September 3, 2026
Trump seeks to refill US oil reserve with Venezuela deal but faces long delay
U.S. President Donald Trump said on the 30th (local time) that he would refill the U.S. Strategic Petroleum Reserve, which has been depleted with…
September 3, 2026
US Navy Official visits South Korean Shipyards in private
With U.S. President Donald Trump pushing a plan to allow overseas construction of U.S. warships, attention is focusing on whether the building of…
September 3, 2026
SES and De Boer Marine expand collaboration with FlexMaritime deployment across Global Markets
SES, a leading space solutions company, and De Boer Marine, a leading provider of top-quality marine equipment and maritime connectivity services,…
September 3, 2026
New ESG guidance to help maritime industry turn sustainability into commercial advantage
New framework helps shipowners and ports align ESG strategy with access to capital, charterer expectations and long-term asset value. Maritime…
September 3, 2026
Britannia P&I Club analysis finds four in five crew deaths linked to illness rather than accidents
New report highlights cardiovascular disease as leading cause of fatalities and raises concerns over mental health risks among younger seafarers.…
September 3, 2026
The Swedish Club launches new Loss Prevention podcast, Knot Another Lesson
The Swedish Club has launched Knot Another Lesson, a new podcast exploring the practical lessons, emerging risks and operational challenges shaping…
September 3, 2026
Lloyd’s Register appoints Jens Grunenberg as Senior Representative for Germany
Lloyd’s Register has appointed Jens Grunenberg as its Senior Representative for Germany, effective 1 September. Based in Hamburg, Grunenberg will…
September 3, 2026
Indian Register of Shipping sets sights on Hamburg for European Expansion
Indian Register of Shipping, a leading international classification society and full member of the International Association of Classification…
September 3, 2026
MOL completes Merger of 6 Ship Management Companies
Unifying Management of Over 200 Vessels and Strengthening Safety Mitsui O.S.K. Lines, announced that it has completed the integration of the MOL…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved