Van Oord’s Deep Dig-It trencher buries cables to 5,5 metres depth for offshore grid connection

Van Oord’s Deep Dig-It trencher crossed the busy shipping route Rotterdam Maasmond successfully and is on its way to offshore Alpha jacket in the Hollandse Kust (zuid) wind farm area. TenneT is building the Hollandse Kust (zuid) offshore grid to connect new offshore wind farms. 4 cables will have to be buried into the North Sea seabed for this purpose. For the first 10 kilometres of the cable route, these cables will have to be buried more than 5 metres into the seabed in order to cross the busy shipping route Rotterdam Maasmond.
The Van Oord-Hellenic Cables consortium will be installing 4 subsea 220 kV AC cables that will connect 2 offshore platforms to the onshore electricity grid. The first 2 cables to the Alpha platform will be installed this year. The other 2 cables, meant for the Beta platform, will follow in 2021. The last few days the preparatory work has been completed. The cable was pulled ashore via a direct drill to the new transformer substation that is being built on the Maasvlakte. From this point, the cable with a total length of 42 kilometres to the wind zone Hollandse Kust (zuid) will be laid by the Deep Dig-It, a large remote-controlled trencher.
Deep Dig-It
Van Oord’s Deep Dig-It is a so-called ‘Tracked Remotely Operated Vehicle’ (TROV) that drives unmanned over the seabed and creates a deep trench for the cables by liquefying the seabed. At the same time, the trencher inserts the cables into the trench and seals them again into the seabed. This new trencher is one of the largest and most powerful of its kind and can bury cables more than 5 metres deep in very hard soil. The Deep Dig-It is controlled at Van Oord’s offshore installation vessel MPI Adventure, which is also equipped with a crane to launch and take out the Deep Dig-It.
Hollandse Kust (South) grid connection
The Hollandse Kust (zuid) offshore wind farm is located 22 kilometres off the coast of the Dutch province of Zuid-Holland. The sea cables connect the two offshore platforms with the Maasvlakte high-voltage substation and the Randstad 380 kV South ring.
The 1,400 MW grid connection will be completed in 2022 and will eventually provide electricity for 1.6 million households. The offshore wind farm contributes significantly to the Dutch government’s objective of having a total of 3.5 GW installed offshore wind energy capacity by 2023. With the commissioning of Borssele Alpha and Beta this year, the first 1.4 GW has been realised.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved























