Neptune begins installing world’s longest heated production pipeline

Neptune Energy today announced installation is underway of the world’s longest heated subsea production pipeline in the Norwegian sector of the North Sea.
Once completed, the 36 kilometre electrically trace-heated (ETH) pipe-in-pipe solution will transport oil from the Neptune Energy-operated Fenja field to the Njord A platform, operated by Equinor.
The first phase of the installation saw a 9km section safely installed and successfully tested.
Neptune Energy’s Director of Projects and Engineering in Norway, Erik Oppedal, said: “The installation and testing of the ETH pipe is a great technical achievement, as well as a milestone in the development of the Fenja field. Norway is an important part of our geographically-diverse portfolio and this is an excellent example of Neptune Energy’s commitment to investing in the region and adopting advanced technologies to overcome challenges.
“The heated pipe-in-pipe solution permits us to tie the field back to existing infrastructure, keeping costs low.”
The length of the ETH pipeline is a significant technological achievement and was developed and qualified through a collaborative approach with TechnipFMC. Due to the high wax content of the Fenja field’s oil, the contents of the pipeline must be warmed up to a temperature above 28-degree Celsius before starting the flow after a shut down. During normal production, the temperature in the pipeline is well above this temperature.
Ståle Ryggvik, TechnipFMC’s Project Director, added: “TechnipFMC is delighted that the extensive qualification program for the ETH Pipe-in-Pipe for Fenja has been successfully completed, and that the first section of the pipe has been installed on the seabed.
“This technology step change has been made possible by the extraordinary effort of TechnipFMC and excellent cooperation with Neptune Energy. It will unlock possibilities to develop future projects with difficult reservoir properties. We are looking forward to continuing the project and completing the installation in 2021.”
The offshore installation was carried out by TechnipFMC’s vessel, Deep Energy, approximately 120km north of Kristiansund, Norway, at a water depth of about 320m.
Partners: Neptune Energy (Operator, 30%), Vår Energi, (45%), Suncor Energy (17.5%), DNO (7.5%)
Related News.
October 19, 2026
OL Shipping Group in Tokyo: Capt. Eberhard Koch calls for realistic solutions to Maritime Decarbonisation
An intensive and engaging couple of days in Tokyo brought together leading figures from the international maritime community, providing a valuable…
October 19, 2026
Regatta for Peace one of the largest ever in Cyprus
Cyprus will host the first European stop on a global sailing journey leading up to the 2027 America’s Cup in Naples. More than 120 sailors…
October 19, 2026
The propulsion technology powering the marine energy transition
The marine industry is under increasing pressure to future-proof fleets, balancing the need to reduce emissions and improve efficiency. Propulsion…
October 19, 2026
Signal Ocean acquires Lgmar
Signal Ocean announced the acquisition of Lgmar, the Athens-based company behind Telix, a maritime email and communication platform in daily use…
October 19, 2026
Canada clean power push challenged by interprovincial grid limits, says GlobalData
Canada is entering a pivotal phase of power-sector expansion as federal tax credits, the phase-out of coal-fired generation, and accelerating…
October 19, 2026
Maritime safety depends on human factors and leadership, not procedures alone
Interim survey findings point to a gap between seafarers’ perceptions of risk and injury data Seafarers may misjudge when and where they are most at…
October 19, 2026
New BIMCO contracts tackle ship recycling and energy-saving retrofits
BIMCO adopted two new contractual solutions designed to help you manage important operational and regulatory challenges: the revised…
October 19, 2026
Stena Line to acquire vessel and make changes to its network
Stena Line has reached an agreement to acquire the RoRo vessel Somerset from CLdN. Subject to closure and transfer, the vessel would begin operating…
October 19, 2026
DORIC WEEKLY INSIGHT 16 OCTOBER 2026
Please find below the DORIC Market Insight for the week ending 16th October 2026. Weekly Report 16.10.2026
October 19, 2026
Important information for port clients and freight carriers effective November 1, a new traffic overpass and port checkpoint will open for traffic to the Port of Riga on Kundziņsala
Starting November 1 of this year, a new traffic overpass connecting Tvaika Street to Kundziņsala will open to facilitate traffic to and from the Port…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved