SeaQuest achieves Chinese dry-docking ahead of schedule

Despite the COVID-19 delays impacting many of China’s repair shipyards, SeaQuest Shipmanagement has ensured that a client’s handysize bulk carrier completed her second special survey, dry-dock and Ballast Water Treatment System (BWTS) retrofit two days ahead of schedule and 7% below budget.
The MV San Felice completed her retrofit on 5th March at COSCO Nantong under the supervision of a SeaQuest team.
The work list included: routine dry-dock works, hull blasting and painting, cargo holds blasting and painting, maintenance of the hatch cover hydraulic system, other minor deck and engine works, and the installation of an Alfa Laval PureBallast BWTS, including ballast lines modification, new electric cabling and remote control system. The duration of the repairs was estimated at 28 days.
The works had originally been scheduled for early December 2019, but were postponed for commercial reasons before COVID-19 struck to 28th January 2020, just ahead of Chinese New Year.
In the last week of January 2020 China was severely hit by COVID-19 and COSCO Nantong, as well as all its subcontractors, were forced to stop all activities until 8th February 2020.
Yard activities were reactivated on 9th February, although many problems had to be overcome: there was a severe lack of local manpower for another couple of weeks. Receiving necessary materials on board was also problematic. At the same time China implemented a travel ban that affected all expatriate superintendents, necessitating the appointment of a Chinese superintendent, recruited from the SeaQuest local team. However, thanks to the excellent relationship between SeaQuest and the yard’s top management, the vessel was included in COSCO “First Priority Vessels” list. Also critical were SeaQuest’s long-standing connections with the domestic industry and technical experts, which meant that MV San Felice was successfully re-delivered to her owners and charterers two days ahead of schedule on 5th March 2020.
“We are proud of our achievement,” said Massimo de Vincenzo, director of SeaQuest’s service centre in Genoa. “It clearly shows how expertise, continuous coordination between owners and managers, a strong local presence and selection of reliable partners enable demanding projects can overcome any hurdle. We are particularly grateful to the master of the MV San Felice and his crew for their high professionalism and commitment during such a critical situation, and to COSCO’s management and staff for the great assistance granted throughout the whole repair period”.
The next vessel under SeaQuest management due for dry-dock, repairs and BWTS retrofit at COSCO is scheduled for 17th March 2020.
Related News.
September 25, 2026
ISLAND OIL: Unveiling of the Sculpture “Cyprus’s Journey Through the Ages” in Protaras – A Tribute and Landmark to Cyprus’s Historical Memory and Cultural Heritage
In a modest ceremony marked by a moving atmosphere, the sculpture “Cyprus’s Journey Through the Ages”, created by acclaimed Cypriot sculptor…
September 25, 2026
World Maritime Day 2026 from Policy to Practice – powering Maritime Excellence
Global regulations will deliver safer, more resilient shipping when they are implemented worldwide. The international maritime community marks…
September 25, 2026
Diana Shipping announces Time Charter Contract for m/v DSI Polaris with Dai An Ocean Shipping
Diana Shipping , a global shipping company specializing in the ownership and bareboat charter-in of dry bulk vessels, announced that, through a…
September 25, 2026
Chief Economists Expect Global Economy to Stabilize, but Fiscal Constraints, Rising Living Costs and AI Investment Uncertainty Threaten Growth
The global economy is stabilizing, but the fiscal support that cushioned successive shocks since 2020 is unlikely to play the same role in the year…
September 25, 2026
V. welcomes its new graduate cohort as programme expands across the group
Twelve graduates from nine nationalities join 11th year of V.’s expanded international management programme. V., the global ship manager and marine…
September 25, 2026
From Policy to Practice: Why Seafarers Are the Key to Maritime Excellence
The shipping industry is no stranger to regulation. Seafarers and ship operators work within a vast framework of international conventions, national…
September 25, 2026
Intermodal Report – Week 38 2026
Please find below the Intermodal market report for week 38 2026. Intermodal Report Week 38 2026 Market Insight By Nikos Tagoulis, Head of…
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved