Scrubber installation waiting list ‘very long’ as IMO 2020 kicks in: Wartsila

There are “very long waiting lists at some shipyards,” particularly in China, for installation of scrubbers on vessels to ensure compliance with IMO 2020 marine fuel regulations, a leading scrubber technologist said this week.
“Scrubbers are made to order and the standard lead time is six months,” Sigurd Jenssen, a director at Wartsila Corporation, a Finland-based marine technologist, said in an interview. Wartsila is a prominent manufacturer of marine scrubbers for wet exhaust gas cleaning, along with other companies including Sweden-based Alfa Laval. After manufacture, the equipment is installed by shipyards, where queues for installation have now built up.
Peter Torstensson, a senior vice president at Alfa Laval, clarified that while his company has capacity and can deliver its Alfa Laval PureSOx scrubber with short lead times, “the rest is a question about the availability at the shipyards, which is a different story and outside our knowledge and control.”
The International Maritime Organization introduced its so-called IMO 2020 fuel regulation January 1 in a move to cut emissions and ocean pollution. This limits sulfur levels in bunker fuels to 0.5% from the previous typical level of 3.5%, in shipping’s biggest regulatory change in decades. A scrubber installation allows a vessel operator to continue to buy cheaper high-sulfur HSFO fuel and separate out the excess sulfur onboard the vessel in what is effectively a mini refinery. The only other alternative is to purchase higher-cost low-sulfur LSFO fuel.
Even though the IMO first announced in 2008 that it planned the sulfur cap, scrubber orders from shipbuilders, owners and operators started to be received only in 2017 for newbuilds and in 2018 for installation on existing vessels, which has resulted in a flurry of orders in the run-up to the deadline, according to Jenssen.
“Shipowners, like everyone else, don’t want to spend any money until they have to,” he said. “Now they don’t have a choice: they need to be fuel-compliant.”
Jenssen estimated that between 3,000 and 4,000 vessels have already ordered scrubbers — including orders already processed — approximately just 10% of the applicable fleet of some 40,000 heavier vessels worldwide that would normally use HSFO.
It typically takes 15-30 days to install a scrubber on a vessel although a large cruise ship could take much longer, according to Jenssen.
A scrubber installation could cost between $1 million and $5 million depending on the vessel and “will absolutely be a viable option…. in the medium term,” given the expected disparities in HSFO and LSFO prices, he said.
Source: PLATTS
Related News.
September 25, 2026
Allied – Weekly Market Review – Week 38
Please find below the Allied Weekly Report for Week 38 | 2026 ALLIED - Weekly Market Report- Week 38
September 25, 2026
Record year on the Northeast Passage but Arctic shipping remains very limited
In 2025, a record 103 transit voyages were made via the Northeast Passage. However, this is still equivalent to only around a day and a half of…
September 25, 2026
[xclusiv] S&P Report 21th September 2026
Please find below the [xclusiv] latest Weekly S&P Report [xclusiv] 2026_09_21 Market Commentary: VLCCs: Freight Boom Reprices the Fleet The VLCC…
September 25, 2026
Grain in Focus US Soybean Sailings to China recover through September
Grain in Focus - US Soybean Sailings to China Recover Through September US soybean sailings to China recovered in September, following the subdued…
September 25, 2026
Marine cargo insurance market continues to soften, reports IUMI
2025 global marine cargo insurance premium indicates that the cargo market softened in that year despite continued growth in the overall premium…
Technical,Technical newsletter
September 25, 2026
Navigator Gas Returns to PrimeServ for New Ethane Retrofits
Eight years of proven service prompt upgrading of two further vessels using Everllence’s trusted retrofit platform Everllence PrimeServ –…
Technical,Technical newsletter
September 25, 2026
LR study points to 200,000m³ LNG carriers as viable next step for global LNG fleet renewal
New analysis finds larger LNG carriers could deliver greater transport efficiency while retaining access to most key LNG terminals worldwide. Lloyd’s…
Technical,Technical newsletter
September 25, 2026
Ocean hull market faces growing risk pressures despite global premium growth, reports IUMI
The global ocean hull insurance market is continuing to soften despite apparent growth in the overall premium base, according to Ilias P.Tsakiris,…
Technical,Technical newsletter
September 25, 2026
Saildrone USVs Receive Danish Flag Registration for European Operations
Saildrone announced that the first four Saildrone Voyager USVs (unmanned surface vehicles) have been registered in Denmark and will operate under…
Technical,Technical newsletter
September 25, 2026
Hiab Unleashes Next-Level Productivity with the MOFFETT M8 NX2: 6,500 lb Powerhouse for North America
Higher Capacity, Same Compact Transport Weight, Delivering Unmatched Job Site Speed, Single-Side Offloading Efficiency, Lower Total Cost of…
Subscribe to our newsletter!
if you dont want to swim alone in the ocean of news, sign up for the newsletter, and you will receive daily all the important news of world shipping!
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved
Design & Development by P.KAN.DESIGNER
© 2026 Cyprus Shipping News. All rights reserved